Superstructure concrete in the bill of quantities
Superstructure concrete comprises the load-bearing elements above ground: columns and concrete walls, floor slabs in their systems, and stairs. Slab systems differ with span and load: a solid slab on beams for short spans and heavy loads, a hordi slab for villas and apartment buildings because it is light and flat underneath, and a flat slab for offices and car parks because it is fast and saves storey height. Concrete walls and shear walls resist wind and earthquake loads in tall buildings, and usually enclose the stairs and lifts.
Where it sits in the bill and what comes before it on site
Its items follow foundation concrete, arranged by element and then by floor. Columns of a floor are not poured until its axes are approved and the concrete below cured, nor a slab until formwork, steel and embedded electrical and plumbing services are inspected.
Items in this category
| Item | Unit |
|---|---|
| Reinforced concrete columns | m³ |
| Concrete walls and shear walls | m³ (or m² of stated thickness) |
| Solid slab and beams | m³ |
| Hordi (ribbed hollow-block) slab | m² (or m³) |
| Flat slab | m³ |
| Concrete stairs | m³ (or m² on plan) |
What is often left out when pricing it
- How long props stay under slabs and the re-propping, which decide how many formwork sets the programme needs.
- Unusual storey heights at entrances and halls, which call for load-bearing scaffolding instead of props.
- Openings and sleeves in slabs and walls and the trimming steel around them, shown only on the services drawings.
- Lifting concrete and steel to upper floors by stationary pump or tower crane.
Frequently asked questions
From where to where is column height measured?
The usual rule measures the column from the top of the slab or tie beam to the soffit of the slab or beam above, and the slab through over columns. Some methods make the column continuous and the slab between its faces. What matters is not counting the junction twice and following the preambles.
Is a hordi slab priced per square or cubic metre?
Both ways. Per square metre, the whole slab area is measured and the rate covers concrete, blocks and steel. Per cubic metre, net concrete less the block volume is measured, with blocks carried in the rate or itemised separately. Two rates are compared only after unifying the unit and knowing what each covers.
Why does the rate per cubic metre differ between elements when the concrete is the same?
Because the concrete itself is the least variable part of the rate; what changes is the steel ratio, the formwork area per cubic metre and placing difficulty. A column, wall or stair needs much formwork for its volume, a raft little, and a flat slab usually carries more steel than a hordi slab.
Related calculators and terms
Other categories in Concrete works
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل