Hordi (ribbed hollow-block) slab in the bill of quantities
| Unit | m² (or m³) |
|---|---|
| Category | Superstructure concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and construct a hordi slab (ribbed hollow-block slab) of 32 cm overall thickness, with concrete hordi blocks 25 cm high, a 7 cm topping and ribs 12 cm wide, in grade C30 concrete; the rate includes the blocks, rib steel, hidden beams, topping mesh, formwork, propping and curing.
Method of measurement
Where the item is per square metre, the whole slab area is measured to its outer faces, including ribs, hidden beams and solid zones, with stair openings and light wells deducted. Where it is per cubic metre, the net concrete is measured: the slab volume at overall thickness less the volume of the blocks. Downstand beams under the slab are measured for the projecting part only.
What the unit rate covers
- Ready-mix concrete to ribs and topping
- Hordi blocks and their placing
- Rib and hidden-beam steel
- Topping mesh
- Formwork, propping and curing
Priced separately
- Downstand beams where given their own item
- Services embedded in the slab
- Waterproofing and roof layers
Specification and reference
A hordi slab is designed as a ribbed (joist) slab to the Saudi Building Code SBC 304, which limits rib width, rib spacing and topping thickness. The project specification sets the block type (concrete, clay or polystyrene) and its weight, and the engineer approves a sample before delivery.
What moves the rate
- Overall thickness and block height
- Block type and weight
- Extent of solid zones and hidden beams
- Rib span and direction
Common pricing mistakes
- Calculating concrete at the overall slab thickness without deducting the block volume, inflating the quantity ordered from the plant.
- Counting blocks over the whole area without excluding hidden beams and the solid zones around columns.
- Estimating slab steel from the ribs alone although the wide hidden beams carry a large share of the steel weight.
- Comparing a rate per square metre with one per cubic metre without conversion, when each covers different things.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Superstructure concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل