Concrete stairs in the bill of quantities
| Unit | m³ (or m² on plan) |
|---|---|
| Category | Superstructure concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for stairs and landings, grade C30, with a waist slab 15 cm thick and steps cast with it at a 17 cm riser and 30 cm going, as shown on the stair details; the rate includes reinforcement and its starter bars from the slabs, inclined formwork, riser forms, propping, vibration and curing.
Method of measurement
In cubic metres, three parts are added: the waist slab at its true inclined length by width by thickness; the step triangles at half the riser by the going by the stair width by the number of steps; and the landings at their area by thickness. Where the item is in square metres, the plan projection of flights and landings is measured. Landing beams are measured with the beams.
What the unit rate covers
- Ready-mix concrete placed by hand or pump
- Reinforcement and starter bars
- Inclined formwork and riser forms
- Propping of flights and landings
- Vibration, curing and protection of step edges
Priced separately
- Marble or other stair finishes
- Balustrades and handrails
- Landing beams and stair core walls
Specification and reference
Stairs are structurally designed to the Saudi Building Code SBC 304, and riser, going, stair width and landing dimensions are governed by the means-of-egress requirements of SBC 201 and SBC 801. Concrete step levels are set so that risers are equal after finishing, allowing for the thickness of the finish.
What moves the rate
- Number of flights and stair shape
- Waist slab thickness
- Storey height
- Pouring the stair with the slab or after it
Common pricing mistakes
- Calculating the waist slab on its plan length instead of its true inclined length, which understates concrete and steel.
- Forgetting the volume of the step triangles and taking only the waist slab and landings in the concrete take-off.
- Pricing the cubic metre at the slab rate although inclined stair formwork and riser forms need far more labour.
- Pouring steps without allowing for the finish thickness, so the first and last risers differ and breaking out or packing is needed.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Superstructure concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل