Solid slab and beams in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Superstructure concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for solid slabs 15 cm thick with downstand and upstand beams, grade C30, as shown on the structural drawings; the rate includes reinforcement, chairs, formwork and propping with steel props until the strength required for striking is reached, leaving openings and sleeves, vibration, levelling and curing.
Method of measurement
The slab is measured over its full area to the outer faces multiplied by its thickness, running through over beams and columns. A beam is measured only for the part projecting below or above the slab, multiplied by its width and its clear length between columns. Stair, light-well and lift openings are deducted; small openings defined by the method of measurement are not.
What the unit rate covers
- Ready-mix concrete, pumping and vibration
- Slab and beam steel and chairs
- Formwork, props and re-propping
- Leaving openings and sleeves
- Levelling the surface and curing
Priced separately
- Embedded electrical and plumbing services
- Waterproofing and screeds to falls above the slab
- Concrete roof parapets where given their own item
Specification and reference
Slabs and beams are designed to the Saudi Building Code SBC 304 for the loads set in SBC 301, and the code gives minimum thickness according to span and support conditions. Steel complies with ASTM A615. The project specification sets when formwork and props may be struck according to the concrete strength achieved, and the curing method in hot weather.
What moves the rate
- Slab thickness and beam depth
- Storey height under the slab
- Number of beams and their intersections
- Number of formwork sets the programme needs
Common pricing mistakes
- Measuring the beam at full depth and then the slab through over it, so the shared part is counted twice.
- Not deducting the stair opening and light wells from the slab area, or deducting them while forgetting the beams around them.
- Overlooking upstand beams and roof parapets cast with the slab because they show on sections, not on plan.
- Assuming one formwork set for all floors although the time props must stay imposes two sets or more.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Superstructure concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل