Reinforced concrete columns in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Superstructure concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for columns on all floors, grade C35 with ordinary Portland cement, to the sections and reinforcement shown in the column schedule and structural drawings; the rate includes vertical bars, ties, smooth-faced formwork with its bracing and plumbing, chamfer strips, vibration and curing.
Method of measurement
The column volume is its section multiplied by its clear height from the top of the slab or tie beam to the soffit of the slab or beam above, floor by floor because the section changes with height. The part within the slab thickness is not counted with the column. Circular columns are taken at their actual sectional area and given a separate item where their rate differs.
What the unit rate covers
- Ready-mix concrete placed by pump or crane
- Vertical bars and ties
- Formwork, bracing and plumbing
- Chamfer strips
- Vibration and curing after striking
Priced separately
- Column necks below tie-beam level
- Column capitals in flat slabs
- Plaster or cladding
Specification and reference
Columns are designed and built to the Saudi Building Code SBC 304, including its reinforcement detailing requirements in seismic zones, with loads taken from SBC 301. Steel complies with ASTM A615 and ready-mix concrete with ASTM C94, and compressive strength is tested on cylinder specimens to ASTM C39. The project specification sets the permitted deviation from plumb.
What moves the rate
- Column section and steel ratio
- Storey height
- Section shape and formwork type
- Strength grade in the lower floors of towers
Common pricing mistakes
- Measuring the column over the full storey height from slab to slab and then measuring the slab through, so the head is counted twice.
- Extending the ground-floor section and steel to every floor although the column schedule reduces both with height.
- Overlooking the closely spaced ties at column ends and in the lap zone, which push the steel weight above the usual allowance.
- Pricing double-height or circular entrance columns at the ordinary column rate without special formwork and scaffolding.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Superstructure concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل