Flat slab in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Superstructure concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for flat slabs 25 cm thick, grade C35, bearing directly on the columns with drop panels around the column heads as shown on the drawings; the rate includes bottom and top steel, additional steel over columns, punching shear reinforcement, chairs, formwork, propping, re-propping and curing.
Method of measurement
The slab area is measured to its outer faces multiplied by its thickness; the volumes of drop panels around columns are added for their thickness beyond the slab, as are column capitals where they exist. Edge beams are measured for the downstand part only. Stair, lift and light-well openings are deducted; service openings below the limit in the method of measurement are not.
What the unit rate covers
- Ready-mix concrete, pumping and surface levelling
- Bottom, top and additional steel
- Punching shear reinforcement
- Chairs for the top mat
- Formwork, propping and re-propping
- Curing for the specified period
Priced separately
- Post-tensioning tendons and accessories where the system is prestressed
- Supporting columns and walls
- Embedded services
Specification and reference
A flat slab is designed to the Saudi Building Code SBC 304 as a two-way slab without beams; its design is governed by punching shear around columns and by deflection limits. Steel complies with ASTM A615. The project specification sets the sequence of striking and re-propping, and no opening is cut near columns after pouring without the designer’s approval.
What moves the rate
- Slab thickness and spans between columns
- Presence of drop panels and capitals
- Steel density over columns
- Formwork system and its cycle time
Common pricing mistakes
- Overlooking the volume and formwork of drop panels, which recur at every column on every floor.
- Pricing steel at a general slab allowance although a flat slab concentrates additional top steel over columns, shown only on the top reinforcement drawing.
- Forgetting punching shear reinforcement and the tall chairs for the top mat because they appear in details, not on plan.
- Comparing its rate with a post-tensioned slab without noticing that tendons and stressing are priced as a separate item.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Superstructure concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل