Plain concrete in the bill of quantities
Plain concrete is unreinforced or lightly reinforced concrete that has no main structural role. Its best-known uses are blinding under foundations, which gives a level, clean surface for fixing steel, and the ground slab bearing on compacted soil, usually reinforced with welded mesh to control shrinkage cracks. It is poured at low strength for blinding and medium strength for floors, with sulphate-resisting cement wherever the soil report shows harmful salts, which is common in coastal areas and sabkha soil.
Where it sits in the bill and what comes before it on site
Blinding comes first in the concrete section, straight after excavation, and the ground slab comes after foundation concrete and backfilling. Blinding is preceded by approval of the excavation bottom; the ground slab by completed backfill and compaction, buried services and soil treatment.
Items in this category
| Item | Unit |
|---|---|
| Blinding concrete | m² of stated thickness (or m³) |
| Slab on grade | m² of stated thickness (or m³) |
What is often left out when pricing it
- The projection of blinding beyond footings and raft on every side, which makes its area larger than the foundation area.
- Extra real consumption from an uneven excavation bottom, unpaid because measurement is on theoretical thickness.
- Contraction and isolation joints in the ground slab: saw cutting and filling with flexible sealant.
- Part-load charges and pump hire when blinding for scattered footings is poured in several visits.
Frequently asked questions
Is blinding measured in square or cubic metres?
It comes both ways: in square metres with the thickness given in the description, or in cubic metres. The risk in the area item is pricing it by mistake at a cubic-metre rate, and in the volume item calculating the quantity without the projection beyond the foundation. Description and unit are read together before pricing.
When is sulphate-resisting cement required in concrete touching the soil?
It is required when the soil and groundwater analyses in the investigation report show a harmful sulphate concentration, and the report names the cement type needed. Many specifications demand it for all below-ground concrete as a precaution. Where sulphates combine with chlorides in sabkha soil, the specification sets a special mix.
Is the mesh reinforcement of the ground slab included in its rate?
In most bills the mesh is named in the ground slab description and is therefore carried in the rate per square metre, together with mesh laps and chairs. Where the reinforcement is ordinary bars and the bill has a separate steel item per tonne, it is measured there. The description and the preambles decide.
Related calculators and terms