Reinforcement and formwork in the bill of quantities
Reinforcement and formwork are the two components that set the rate of reinforced concrete more than the concrete itself. Reinforcement is high-strength deformed bars delivered in 12 m lengths and cut and bent to bar bending schedules, or welded mesh for floors. Formwork is the temporary mould that shapes concrete until it hardens: traditional timber of plywood and battens suits villas and non-repeating shapes, while steel or system formwork suits towers and repeated elements because it is quick to erect and reused many times.
Where it sits in the bill and what comes before it on site
They appear as separate items after the concrete where the bill separates them, or are merged into the cubic-metre rate. Supply is preceded by approval of bar bending schedules, formwork drawings and samples, and pouring by the engineer’s inspection of steel and formwork.
Items in this category
| Item | Unit |
|---|---|
| Reinforcing steel | tonne (or kg) |
| Formwork | m² of contact area |
What is often left out when pricing it
- Chairs, concrete spacers and tying wire, consumed with the steel but not measured in most bills.
- Cutting waste from the 12 m stock length, which varies widely with the lengths of pieces required.
- Release agent, form ties, chamfer strips and materials for sealing joints between panels.
- The decline of plywood sheets with every use until they must be replaced before the project ends.
Frequently asked questions
Are lap splices and chairs paid within the steel weight?
Usually lap splices shown on the approved drawings are measured within the weight, while chairs, spacers, tying wire and waste are not and are carried in the rate per tonne. Some bills, however, provide for net lengths without laps. The wording of the preambles settles the matter before the rate is built.
How is formwork measured when it has its own item?
It is measured by the contact area between form and concrete: sides of footings and tie beams, the column perimeter by its height, slab soffits, and beam sides and soffits. Surfaces cast against soil or blinding and exposed top surfaces are not measured. It is classified by element because the cost of each type differs.
Is steel paid by actual or theoretical weight?
By theoretical weight: lengths from approved bar bending schedules multiplied by the standard weight per metre for each diameter. Purchase from the mill or supplier is by actual weighbridge weight, which may differ from the theoretical within the permitted rolling tolerance. The contractor bears this difference and allows for it in the rate analysis.
Related calculators and terms
Other categories in Concrete works
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل