Concrete walls and shear walls in the bill of quantities
| Unit | m³ (or m² of stated thickness) |
|---|---|
| Category | Superstructure concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for concrete walls, shear walls and stair and lift core walls, 25 cm thick, grade C35, as shown on the structural drawings; the rate includes the two layers of vertical and horizontal steel, boundary reinforcement, formwork to both faces with its ties and plugging of tie holes, forming openings, vibration and curing.
Method of measurement
The wall volume is its length multiplied by its clear height between slabs and by its thickness. Door and window openings larger than the area set in the method of measurement are deducted; small openings and sleeves are not. Columns embedded in the wall ends are counted with the wall where they are of the same thickness, and with the columns where they project from its face.
What the unit rate covers
- Ready-mix concrete placed in lifts
- Vertical, horizontal and boundary steel
- Formwork to both faces with its ties
- Forming openings and their trimming steel
- Plugging tie holes and curing
Priced separately
- Waterproofing of basement walls
- Waterstops where given their own item
- Backfilling behind retaining walls
Specification and reference
Shear walls and concrete walls are designed to the Saudi Building Code SBC 304 to resist the lateral loads calculated under SBC 301, and earth-retaining walls with regard to SBC 303. Steel complies with ASTM A615. The project specification sets the height of each lift, the positions of construction joints and the treatment of tie holes in watertight walls.
What moves the rate
- Wall thickness and height
- Steel density at the boundaries
- Number of openings
- Formwork type and number of reuses
Common pricing mistakes
- Pricing a shear wall at the steel ratio of an ordinary wall although its ends are reinforced like columns with closely spaced ties.
- Deducting door openings from the concrete and forgetting the formwork to the reveals and the trimming steel around them.
- Pricing basement wall formwork at the ordinary wall rate although single-sided formwork against the shoring needs special bracing.
- Pricing lift shaft walls as an open wall although their inner formwork works in a confined space to tight plumb tolerances.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Superstructure concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل