العربية Try the demo Start now
Home › BOQ items guide › Concrete works › Foundation concrete

Foundation concrete in the bill of quantities

Foundation concrete comprises the reinforced elements that carry the building loads to the soil: isolated, combined and strip footings and the raft, with the column necks and the tie beams that link them. Isolated footings are chosen where the soil is good and loads moderate, as in villas; a raft where the soil is weak, footings would nearly touch, or there is a basement and groundwater; and piles where the sound stratum is deep. These elements are usually poured with sulphate-resisting cement and waterproofed on faces touching the soil.

Where it sits in the bill and what comes before it on site

Its items follow blinding and precede superstructure concrete, in construction order: footings or raft, then column necks, then tie beams. Before pouring, the blinding is approved and the axes set out on it, any membrane under the raft laid, and steel and formwork inspected.

Items in this category

ItemUnit
Isolated footingsm³
Raft foundationm³
Tie beams (ground beams)m³ (or lin. m by section)
Column necksm³

What is often left out when pricing it

Frequently asked questions

Does the rate per cubic metre of foundation concrete include the reinforcement?

It differs between bills. Many government and villa bills make the rate per cubic metre include steel and formwork, so the contractor takes the steel ratio of each element from the drawings. Others give steel its own item per tonne and formwork per square metre. Rates are not compared before knowing which method applies.

How is double counting of concrete avoided where column necks meet tie beams?

One rule is applied on every axis: the neck is measured continuous from footing top to tie-beam top, and the tie beam over its clear length between neck faces. The junction is thus counted once, within the neck. Tie-beam intersections are treated alike: one runs through, the other stops at its face.

Apart from quantity, what makes a raft pour cost more than isolated footings?

A continuous pour of large volume, with the several pumps, standby pump and steady supply from more than one plant it needs; night pouring in hot weather; measures to control the temperature of thick concrete; heavy steel chairs; waterstops at construction joints; and the membrane under the raft with its protection layer.

Related calculators and terms

Other categories in Concrete works

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل