Temporary site hoarding in the bill of quantities
| Unit | lin. m (or lump sum) |
|---|---|
| Category | Site preparation |
| Division | Site preparation and earthworks |
The item as worded in the bill
Supply and erect a temporary hoarding around the site, 2.4 m high, of corrugated galvanised steel sheets fixed to steel posts and rails on concrete bases, with a vehicle gate, a personnel door, the project signboard and warning lights as the municipality requires; the rate includes maintenance throughout the project and removal on completion.
Method of measurement
The actual length of the hoarding is measured along its centre line around the site perimeter; the height is fixed by the item description and is not measured. Gates are counted within the length unless a separate item by number is given. Relocating or re-erecting the hoarding for construction phases is not paid unless the contract says so, and the hoarding remains the contractor’s property after dismantling.
What the unit rate covers
- Sheets, posts and rails
- Concrete bases and their excavation
- Gates and locks
- Project signboard and warning lights
- Maintenance and repainting during the contract
- Dismantling, removal and making good the ground
Priced separately
- Fees for a pavement or street occupation permit, if any
- Guarding and surveillance cameras
- The permanent boundary wall
Specification and reference
The hoarding is subject to the requirements of the municipality that issued the building permit regarding height, colour, signboard and not encroaching on the pavement, and to the provisions for protecting pedestrians and adjoining property during construction in the Saudi Building Code SBC 201. The project specification sets the sheet thickness and the post spacing.
What moves the rate
- Hoarding height and sheet thickness
- Project duration and number of relocations
- Number and size of gates
- Ground conditions at the bases
Common pricing mistakes
- Pricing the hoarding as fully consumed although most of its sheets and posts are reused on another project.
- Ignoring the cost of moving the hoarding more than once when external works or service lines run along the boundary.
- Forgetting the project signboard, the wide truck gate and the warning lights that the municipality requires with the hoarding.
- Pricing it per linear metre in its own item while also loading its cost on the preliminaries, inflating the tender.
Related calculators and terms
More items in Site preparation
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل