Imported fill and soil replacement in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Backfilling and compaction |
| Division | Site preparation and earthworks |
The item as worded in the bill
Supply, spread and compact clean selected soil from outside the site, granular and free of organic matter and harmful salts, of class A-1-a, A-1-b or A-2-4, to replace unsuitable soil below founding level, in layers not exceeding 25 cm compacted to 95% of maximum dry density, including testing.
Method of measurement
The compacted in-place volume is measured from the difference between levels surveyed before spreading and after compaction, within the replacement limits shown on the drawings or in the soil report, including the lateral extension beyond the foundation edges. Truck delivery tickets and loose volume are not relied on. Excavating and hauling the unsuitable soil is measured under the excavation item unless merged into this one.
What the unit rate covers
- Supplying selected soil from an approved source
- Transport to site and spreading
- Watering and compaction in layers
- Classification and density tests
- Level surveys before spreading and after compaction
Priced separately
- Excavating and hauling the unsuitable soil
- Plate load test, if required
- Geotextile separation layers
Specification and reference
The soil report sets the depth and extent of replacement, the fill type and the degree of compaction, under the Saudi Building Code SBC 303. The material is classified under the AASHTO system or the Unified Soil Classification System, ASTM D2487, with density controlled by the modified Proctor test, ASTM D1557. The engineer approves source and sample before delivery.
What moves the rate
- Distance of the borrow source from the site
- Depth of replacement and its lateral extension
- Required class and degree of compaction
- Total quantity and continuity of supply
Common pricing mistakes
- Buying soil by the loose truckload and pricing the item on the same volume, although the paid compacted volume is clearly smaller.
- Calculating replacement on the footing area only although the soil report extends its limits beyond the foundation edge on every side.
- Overlooking that excavating and hauling the weak soil is a separate item, or pricing it twice, here and under excavation.
- Relying on a nearby source before its soil classification is tested, then having the material rejected and moving to a farther source.
Related calculators and terms
More items in Backfilling and compaction
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل