Unitm² of floor area (or m³ or lump sum)
CategorySite preparation
DivisionSite preparation and earthworks

The item as worded in the bill

Demolish an existing two-storey building of reinforced concrete and blockwork down to the underside of its foundations, using mechanical plant with water spraying to suppress dust and with protection of adjoining buildings, including breaking up, loading and hauling the debris to the approved dump; the rate includes disconnecting services, obtaining the demolition permit and filling the resulting voids.

Method of measurement

The built floor area is measured for each storey separately over the external faces of the walls and then added together; boundary walls and annexes are not measured unless named in the item. Foundations are deemed included down to the stated depth, and anything deeper is measured in cubic metres. The rate is not adjusted for the value of salvage passing to the contractor.

What the unit rate covers

Priced separately

Specification and reference

Demolition requires a demolition permit from the municipality and disconnection of services by their owners. The provisions of the Saudi Building Code SBC 201 for protecting neighbours and the public during demolition apply, and the contractor submits a method statement showing the demolition sequence and the measures against uncontrolled collapse.

What moves the rate

Common pricing mistakes

Related calculators and terms

More items in Site preparation

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل