Demolition of existing buildings and debris removal in the bill of quantities
| Unit | m² of floor area (or m³ or lump sum) |
|---|---|
| Category | Site preparation |
| Division | Site preparation and earthworks |
The item as worded in the bill
Demolish an existing two-storey building of reinforced concrete and blockwork down to the underside of its foundations, using mechanical plant with water spraying to suppress dust and with protection of adjoining buildings, including breaking up, loading and hauling the debris to the approved dump; the rate includes disconnecting services, obtaining the demolition permit and filling the resulting voids.
Method of measurement
The built floor area is measured for each storey separately over the external faces of the walls and then added together; boundary walls and annexes are not measured unless named in the item. Foundations are deemed included down to the stated depth, and anything deeper is measured in cubic metres. The rate is not adjusted for the value of salvage passing to the contractor.
What the unit rate covers
- Demolition permit and disconnection of services
- Mechanical demolition and breaking up
- Water spraying and protective screens
- Loading and hauling debris to the dump
- Removing foundations to the stated depth
- Filling voids and levelling the ground
Priced separately
- Removal of hazardous materials such as asbestos sheets
- Underpinning or propping of abutting neighbouring buildings
- Removal of concealed buried tanks and septic tanks
Specification and reference
Demolition requires a demolition permit from the municipality and disconnection of services by their owners. The provisions of the Saudi Building Code SBC 201 for protecting neighbours and the public during demolition apply, and the contractor submits a method statement showing the demolition sequence and the measures against uncontrolled collapse.
What moves the rate
- Type of construction and number of storeys
- Closeness of neighbouring buildings and street width
- Foundation depth and presence of a basement
- Value of saleable salvage
Common pricing mistakes
- Pricing demolition on the plot area instead of the total floor area, so a three-storey building is priced as one storey.
- Assuming a load-bearing block structure and then finding a reinforced concrete frame that needs heavier breakers and more time.
- Overlooking the underground tank, septic tank and deep foundations, which leave voids that need filling and compaction in layers.
- Estimating debris from the solid volume of walls without allowing for bulking after breaking when counting truck trips.
Related calculators and terms
More items in Site preparation
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل