Trench excavation for services in the bill of quantities
| Unit | lin. m by depth band (or m³) |
|---|---|
| Category | Excavation |
| Division | Site preparation and earthworks |
The item as worded in the bill
Excavate trenches for drainage and water pipes and electrical cables in any soil other than rock, to the width given in the typical sections and to a depth not exceeding 1.5 m, including grading and trimming the bottom to falls, supporting the sides where needed, protecting existing crossing services, stockpiling the material beside the trench and hauling the surplus.
Method of measurement
Trench length is measured along the centre line of the run between manholes and classified by the band of average depth from ground surface to trench bottom. Where the item is in cubic metres, the length is multiplied by the theoretical width in the typical section and by the average depth, with no addition for slopes or widening at joints. Manhole excavation is measured under its own item.
What the unit rate covers
- Excavation to the specified width and depth
- Grading and trimming the bottom to falls
- Temporary side support
- Protecting existing crossing services
- Barriers and warning signs around the trench
Priced separately
- Sand bedding and pipe surround
- Backfilling and warning tape
- Cutting and reinstating asphalt or paving
- Manhole excavation
Specification and reference
Trenching, pipe bedding and cover for drainage and water lines are covered by the Saudi Building Code SBC 701, and cable trenches follow the Saudi Electricity Company’s requirements, with the typical sections on the project drawings. An excavation permit from the municipality is required for work outside the property boundary, and deep-trench safety requirements apply.
What moves the rate
- Trench depth and width
- Density of existing crossing services
- Type of surface to be cut and reinstated
- Length of run and continuity of work
Common pricing mistakes
- Pricing the whole trench by excavator although areas crossing existing services are dug by hand at far lower output.
- Taking one depth for the whole drainage run although the pipe fall deepens it gradually into a higher band.
- Forgetting asphalt cutting and reinstatement at street crossings because they are not in the excavation item itself.
- Using the theoretical width in the rate although deep trenches are actually dug wider to let workers in and fit the supports.
Related calculators and terms
More items in Excavation
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل