Backfilling and compaction in layers in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Backfilling and compaction |
| Division | Site preparation and earthworks |
The item as worded in the bill
Backfill around foundations and under ground slabs with clean approved soil from the excavation, spread in layers not exceeding 25 cm each, including watering and mechanical compaction to not less than 95% of maximum dry density; the rate includes field density tests on every layer.
Method of measurement
The compacted in-place volume is measured geometrically: the paid excavation volume less the volume of buried concrete and masonry, plus filling above ground level up to the underside of the ground slab. No allowance is added for shrinkage on compaction or for filling working space and slopes whose excavation was not paid in the first place.
What the unit rate covers
- Loading soil from stockpiles and spreading it
- Watering to optimum moisture content
- Compaction with rollers and plate compactors
- Field density tests
- Re-compacting rejected layers
Priced separately
- Supplying soil from outside the site
- Sand surround to pipes
- Waterproofing foundations before backfilling
Specification and reference
Backfill requirements and degree of compaction are set in the Saudi Building Code SBC 303, the soil report and the project specification. Maximum dry density is determined by the modified Proctor test to ASTM D1557, and field density by the sand-cone method to ASTM D1556 or by nuclear gauge, at the test frequency set in the inspection plan.
What moves the rate
- Suitability of excavated material or need to import
- Required compaction and layer thickness
- Tightness of fill areas between elements
- Availability of water on site
Common pricing mistakes
- Taking the backfill quantity as equal to the excavation without deducting footings, column necks, tie beams and blinding.
- Forgetting the fill under the ground slab above natural ground level when the ground floor level is raised.
- Pricing compaction at roller output for open areas although most of the fill is confined between tie beams.
- Assuming all excavated material is fit for backfill before testing, then having to import soil that was never priced.
Related calculators and terms
More items in Backfilling and compaction
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل