Excavation for footings and foundations in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Excavation |
| Division | Site preparation and earthworks |
The item as worded in the bill
Excavate for isolated and strip footings and tie beams in any soil other than rock down to the founding level shown on the drawings, to a depth not exceeding 2 m, including trimming the sides, levelling and compacting the bottom, stockpiling suitable material for backfill and hauling the surplus to approved dumps; the rate includes temporary side support where needed.
Method of measurement
The net geometric volume is measured: the plan area of the blinding as drawn multiplied by the depth from ground level after levelling to the underside of the blinding. No addition is made for working space, side slopes or bulking unless the preambles say so. Where the bill splits excavation into depth bands, each part is taken in its own band.
What the unit rate covers
- Machine excavation and hand digging where needed
- Trimming sides and levelling the bottom
- Compacting the bottom of excavation
- Stockpiling material suitable for backfill
- Hauling surplus to the approved dump
- Keeping out rain and surface water
Priced separately
- Excavation in rock
- Groundwater dewatering
- Permanent or engineered shoring
- Soil replacement below founding level
Specification and reference
Foundation excavation is governed by the Saudi Building Code SBC 303 on soils and foundations and by the recommendations of the project’s approved soil report, in particular the founding level, safe side slopes and treatment of weak soil. The engineer approves the excavation bottom before pouring, and compaction tests are made on it under the inspection and test plan.
What moves the rate
- Soil type and cohesion
- Depth of excavation and spacing of footings
- Haul distance for surplus
- Tightness of the site and stockpile space
Common pricing mistakes
- Dividing the real digging cost by the paid quantity without noticing that the volume actually dug, with working space and slopes, is far larger.
- Taking the depth from natural ground level although levelling or topsoil stripping has already been paid under another item.
- Pricing closely spaced footings as separate pits when the work will really be one open cut, which increases backfill later.
- Ignoring the soil report’s note of loose sandy soil whose sides collapse and need flatter slopes.
Related calculators and terms
More items in Excavation
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.