Excavation for footings and foundations in the bill of quantities

Unitm³
CategoryExcavation
DivisionSite preparation and earthworks

The item as worded in the bill

Excavate for isolated and strip footings and tie beams in any soil other than rock down to the founding level shown on the drawings, to a depth not exceeding 2 m, including trimming the sides, levelling and compacting the bottom, stockpiling suitable material for backfill and hauling the surplus to approved dumps; the rate includes temporary side support where needed.

Method of measurement

The net geometric volume is measured: the plan area of the blinding as drawn multiplied by the depth from ground level after levelling to the underside of the blinding. No addition is made for working space, side slopes or bulking unless the preambles say so. Where the bill splits excavation into depth bands, each part is taken in its own band.

What the unit rate covers

Priced separately

Specification and reference

Foundation excavation is governed by the Saudi Building Code SBC 303 on soils and foundations and by the recommendations of the project’s approved soil report, in particular the founding level, safe side slopes and treatment of weak soil. The engineer approves the excavation bottom before pouring, and compaction tests are made on it under the inspection and test plan.

What moves the rate

Common pricing mistakes

Related calculators and terms

More items in Excavation

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل