Bulk excavation for basements in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Excavation |
| Division | Site preparation and earthworks |
The item as worded in the bill
Open bulk excavation for the basement in any soil other than rock from existing ground level to the underside of the raft blinding, to a depth of up to 5 m, in stages coordinated with the shoring works, including forming and later removing a plant access ramp, hauling the excavated material to approved dumps, and levelling and compacting the bottom.
Method of measurement
The volume is calculated from the grid of ground levels surveyed before excavation and the design bottom level, within the outer face of the blinding or the shoring line shown on the drawings. The temporary ramp, over-excavation beyond those limits and side slopes are not measured. Lift pits and pump rooms below the general bottom level are added at their net dimensions.
What the unit rate covers
- Staged excavation by excavators
- Loading and hauling excavated material to the dump
- Plant access ramp and its removal
- Levelling and compacting the bottom
- Managing truck movement and cleaning surrounding streets
Priced separately
- Shoring of the excavation sides
- Groundwater dewatering
- Excavation in rock
- Backfilling behind basement walls
Specification and reference
Deep excavation is subject to the requirements of the Saudi Building Code SBC 303 for excavations and protection of adjoining structures, and to the soil report’s recommendations on side slopes and groundwater level. City municipalities require the shoring system to be approved before digging next to neighbours and streets, and settlement of adjacent buildings is monitored throughout the excavation.
What moves the rate
- Depth of excavation and number of stages
- Dump distance and truck-ban hours
- Groundwater level
- Site tightness and room for a ramp
Common pricing mistakes
- Multiplying the basement area by one average depth on sloping land instead of calculating from the actual grid of levels.
- Overlooking excavation of the temporary ramp and its later filling or removal in the last stage by a machine working from above.
- Counting truck trips over a full working day although the municipality bans trucks during peak hours.
- Assuming a dry excavation in a coastal city such as Jeddah or Dammam without checking the water level in the soil report.
Related calculators and terms
More items in Excavation
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل