Bulk excavation for basements in the bill of quantities

Unitm³
CategoryExcavation
DivisionSite preparation and earthworks

The item as worded in the bill

Open bulk excavation for the basement in any soil other than rock from existing ground level to the underside of the raft blinding, to a depth of up to 5 m, in stages coordinated with the shoring works, including forming and later removing a plant access ramp, hauling the excavated material to approved dumps, and levelling and compacting the bottom.

Method of measurement

The volume is calculated from the grid of ground levels surveyed before excavation and the design bottom level, within the outer face of the blinding or the shoring line shown on the drawings. The temporary ramp, over-excavation beyond those limits and side slopes are not measured. Lift pits and pump rooms below the general bottom level are added at their net dimensions.

What the unit rate covers

Priced separately

Specification and reference

Deep excavation is subject to the requirements of the Saudi Building Code SBC 303 for excavations and protection of adjoining structures, and to the soil report’s recommendations on side slopes and groundwater level. City municipalities require the shoring system to be approved before digging next to neighbours and streets, and settlement of adjacent buildings is monitored throughout the excavation.

What moves the rate

Common pricing mistakes

Related calculators and terms

More items in Excavation

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل