Sprayed polyurethane foam insulation in the bill of quantities
| Unit | m² |
|---|---|
| Category | Thermal insulation |
| Division | Waterproofing and thermal insulation |
The item as worded in the bill
Supply and spray rigid closed-cell polyurethane foam to the building roof to an average thickness of 5 cm and not less than the specified density, on a clean dry surface, turned up the parapet and around plinths and outlets, then covered with a flexible sunlight-protective coating in two coats; the rate includes protecting façades and equipment from overspray.
Method of measurement
Measured in square metres of the area actually sprayed: the net horizontal area plus upstands on the parapet and plinths, with the thickness stated. Thickness is probed at scattered points the engineer chooses, and the item states whether an average or a minimum at every point is required. A protective coating included in the item is not measured separately. Nothing is added for surface unevenness or filling depressions.
What the unit rate covers
- Cleaning the surface and confirming it is dry
- Spraying in passes to the required thickness
- Upstands on the parapet and around plinths and outlets
- Sunlight-protective coating
- Masking façades, equipment and nearby vehicles against overspray
- Thickness and density checks
Priced separately
- Screed to falls under the foam
- A separate waterproof membrane where the specification requires one
- Protection screed or tiles over the foam
Specification and reference
Sprayed foam conforms to ASTM C1029, and the project technical specification sets the density, sprayed thickness and protective coating type. The roof thermal resistance required under the energy conservation code SBC 601 or 602 is consulted, with the fire requirements for foam plastics in Saudi Building Code SBC 201. A specialist crew with calibrated spraying equipment executes the work.
What moves the rate
- Thickness and density required
- Evenness of the surface and the extra material it consumes
- Type of protective coating and number of coats
- Roof area and cost of mobilising the spraying equipment
Common pricing mistakes
- Calculating material on the nominal thickness although depressions and surface unevenness consume extra foam that is not paid for.
- Omitting the protective coating to lower the rate although exposed foam breaks down under the sun within months.
- Ignoring stoppage of spraying on windy or humid days and its effect on how long the equipment and crew stay.
- Pricing a small roof at the rate of large areas although the cost of bringing spraying equipment is fixed.
Related calculators and terms
More items in Thermal insulation