Modified bitumen membrane to roofs in the bill of quantities
| Unit | m² |
|---|---|
| Category | Roof waterproofing |
| Division | Waterproofing and thermal insulation |
The item as worded in the bill
Supply and install roof waterproofing in polyester-reinforced polymer-modified bitumen membrane 4 mm thick, torch-applied over the primed screed to falls, turned up the parapet at least 20 cm above finished level and terminated with an aluminium flashing strip and sealant; the rate includes treatment of roof outlets and a 48-hour flood test.
Method of measurement
Measured in square metres of the net horizontal roof area between the inner parapet faces, plus the upstands on the parapet, stair room walls and equipment plinths unless upstands have a linear-metre item of their own. Nothing is added for laps or falls. Outlets and small penetrations are not deducted. The stair room and lift room roof is measured under the same item.
What the unit rate covers
- Bituminous primer over the screed to falls
- Membrane sheets torch-welded with side and end laps
- Angle fillets where the roof meets the parapet
- Upstands terminated with a metal strip and sealant
- Treatment of outlets and penetrating pipes
- Flood test and repair of defects
Priced separately
- Screed to falls
- Thermal insulation and separation layer
- Roof tiles or protection layer
- Treatment of roof expansion joints
Specification and reference
The project specification and the manufacturer’s approved data sheet apply, together with the roof covering and roof drainage requirements of Saudi Building Code SBC 201. The specification sets the polymer modification type, reinforcement weight and heat resistance of the sheets to suit Saudi Arabia’s hot climate. A manufacturer-approved applicator executes it and gives a joint warranty on material and workmanship.
What moves the rate
- Number of layers, sheet thickness and type
- Extent of upstands relative to the horizontal area
- Number of equipment plinths and penetrations
- Building height and means of hoisting the rolls
Common pricing mistakes
- Measuring the horizontal area alone and forgetting upstands on the parapet, stair room walls and air-conditioner plinths.
- Buying rolls for the measured area with no extra for laps and corner strips, so a shortfall appears during the work.
- Overlooking the stair room and lift room roof and concrete entrance canopies, which are waterproofed in the same material.
- Not allowing for the flood test period, plugging the outlets and providing water on the roof within the item’s cost.
Related calculators and terms
More items in Roof waterproofing