Liquid-applied roof membrane in the bill of quantities
| Unit | m² |
|---|---|
| Category | Roof waterproofing |
| Division | Waterproofing and thermal insulation |
The item as worded in the bill
Supply and apply liquid polyurethane roof waterproofing in two or more coats to the specified dry film thickness, over a primer suited to the substrate, with corners, outlets and cracks reinforced with polyester fabric and the membrane turned up the parapet and equipment plinths; the rate includes surface preparation, a sunlight-resistant top coat and a flood test.
Method of measurement
Measured in square metres of the surface actually coated, horizontal and vertical: the net roof area plus upstands on the parapet, walls and equipment plinths to the detailed height. The area is not multiplied by the number of coats, and reinforcing fabric and primer are not measured separately. Acceptance rests on the measured dry film thickness or the material consumed per square metre, not the coat count.
What the unit rate covers
- Cleaning the surface and repairing cracks and holes
- Primer suited to the substrate type and moisture
- Liquid membrane coats to the required thickness
- Reinforcing fabric at corners, outlets and joints
- Sunlight-resistant top coat
- Flood test
Priced separately
- Screed to falls and its major repair
- Thermal insulation
- Protection layer or tiles over the membrane
Specification and reference
The manufacturer’s approved data sheet, read with the project specification, sets the dry film thickness, coverage and permissible substrate moisture at application; roof covering requirements are in Saudi Building Code SBC 201. On exposed roofs the material or its top coat must resist ultraviolet radiation and high temperature.
What moves the rate
- Material type: polyurethane, acrylic or modified bitumen
- Dry film thickness required
- Roughness and porosity of the substrate
- Number of details and penetrations
Common pricing mistakes
- Pricing two coats at a light coverage although the specification sets a dry thickness that only a larger quantity achieves.
- Assuming a smooth surface although rough screed absorbs primer and consumes more material than the data sheet states.
- Leaving out the sunlight-resistant top coat on exposed roofs, so the membrane deteriorates within the warranty period.
- Applying over a screed that has not dried, then bearing the cost of removing blisters and redoing the work.
Related calculators and terms
More items in Roof waterproofing
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل