Bituminous coating to foundations in the bill of quantities
| Unit | m² |
|---|---|
| Category | Foundation waterproofing |
| Division | Waterproofing and thermal insulation |
The item as worded in the bill
Supply and apply to all concrete and block surfaces in contact with soil, including footings, column necks, ground beams and walls below ground level, a primer and two coats of cold-applied bituminous paint at the coverage in the manufacturer’s data sheet, after cleaning surfaces, repairing defects and plugging formwork tie holes; the rate includes protecting the coating until backfilling.
Method of measurement
Measured in square metres of the surface actually coated, not the plan area: footing top and four sides, neck perimeter over its buried height, both sides of the ground beam and its top if buried, and both faces of block walls below ground. The footing underside and the part of its top under the neck are not measured. The area is measured once whatever the number of coats.
What the unit rate covers
- Cleaning the surface and removing dust and loose material
- Plugging formwork tie holes and repairing minor honeycombing
- Primer coat
- Two coats of bituminous paint with drying time between them
- Protecting the coating from damage until backfilling
Priced separately
- Polyethylene sheeting under footings
- Protection boards where the specification requires them
- Backfilling and compaction
- Treatment of major structural defects in the concrete
Specification and reference
The project technical specification and the approved manufacturer’s data sheet govern, setting the number of coats, coverage and drying time. The soil report’s recommendations and the damp-protection requirements for foundations in SBC 201 and 303 are consulted, with SBC 304 for the durability of concrete exposed to sulphates and chlorides. Asphalt primer conforms to ASTM D41.
What moves the rate
- Number of coats and coverage required
- Type of paint: water-based emulsion or solvent-based
- Roughness of the concrete surface and repair needed
- Excavation depth and tight working space around footings
Common pricing mistakes
- Taking the area from the plan of the footings and ignoring their sides, the neck perimeters and both sides of the ground beams.
- Pricing one coat although the item states a primer and two coats, which multiplies material and labour consumption.
- Forgetting both faces of solid block walls below ground, an area that sometimes approaches that of the coated concrete.
- Using the theoretical coverage for a smooth surface although rough concrete and blockwork consume more.
Related calculators and terms
More items in Foundation waterproofing