Bituminous membrane to foundations in the bill of quantities
| Unit | m² |
|---|---|
| Category | Foundation waterproofing |
| Division | Waterproofing and thermal insulation |
The item as worded in the bill
Supply and install waterproofing to the raft and basement walls in polyester-reinforced modified bitumen membrane 4 mm thick, torch-applied on a primed surface with 10 cm side laps and 15 cm end laps, with angle fillets and reinforcing strips; the rate includes a protection screed over the horizontal membrane and protection boards to the vertical membrane before backfilling.
Method of measurement
Measured in square metres of the net area waterproofed, laps and reinforcing strips not added. Horizontally it is the blinding area covered under the raft plus the jointing projection; vertically it runs from the raft underside to the termination above ground level per the section. Sides and bottoms of lift pits and sumps are added. The area is not multiplied by the number of layers.
What the unit rate covers
- Bituminous primer on a clean dry surface
- Membrane sheets torch-welded with laps
- Mortar angle fillets at corners and reinforcing strips
- Protection screed over the horizontal membrane
- Protection boards to the vertical membrane
- Treatment of pipe penetrations
Priced separately
- Blinding concrete under the membrane
- Dewatering
- Waterstops in construction joints
- Backfilling and compaction after waterproofing
Specification and reference
The item is governed by the project technical specification and the manufacturer’s data sheet, and by the Saudi Building Code requirements in SBC 201 and 303 for waterproofing below-ground structures under water pressure. The soil report’s groundwater level decides the number of layers. Primer conforms to ASTM D41, and a manufacturer-approved applicator executes the work and provides a warranty.
What moves the rate
- Number of layers, membrane thickness and reinforcement type
- Basement depth and height of the waterproofed walls
- Groundwater level and difficulty of keeping the surface dry
- Number of pits, penetrations and corners
Common pricing mistakes
- Pricing one layer although the specification requires two layers with staggered joints below the groundwater level.
- Leaving out the protection screed and protection boards although the item includes them and their area equals the membrane area.
- Forgetting the sides of deep lift pits and sumps, which add appreciably to the vertical area.
- Measuring the vertical part to ground level only although the detail carries the membrane above it and fixes its edge.
Related calculators and terms
More items in Foundation waterproofing
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل