Slab on grade in the bill of quantities
| Unit | m² of stated thickness (or m³) |
|---|---|
| Category | Plain concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour concrete for the ground slab on compacted soil, 15 cm thick, grade C25, reinforced with welded steel mesh of 8 mm bars at 20 cm both ways, power-floated, with sawn contraction joints and isolation joints around columns filled with flexible sealant; the rate includes the mesh, chairs and curing.
Method of measurement
The net area of the slab is measured between the inner faces of the tie beams or walls bounding it, or over them where the slab runs across them on the drawings. Column positions and small openings defined by the method of measurement are not deducted. Mesh laps, thickenings under partitions and joints are not measured unless separate items are given.
What the unit rate covers
- Ready-mix concrete and its pumping
- Welded mesh with its laps and chairs
- Level control and power floating
- Contraction and isolation joints and their filling
- Curing straight after the pour
Priced separately
- Filling and compaction under the slab
- Polyethylene sheet where given its own item
- Surface hardeners or epoxy coating
- Thermal insulation under the slab, if any
Specification and reference
Concrete materials and workmanship follow the Saudi Building Code SBC 304, and the soil under the slab is prepared to SBC 303 and the soil report. Welded mesh complies with ASTM A1064 and ready-mix concrete with ASTM C94. The project specification sets the required surface flatness, the joint spacing and the curing method in hot weather.
What moves the rate
- Slab thickness and mesh weight
- Surface flatness and type of finish
- Number and spacing of joints
- Area of each pour and ease of access
Common pricing mistakes
- Calculating mesh on the net area without the lap of meshes between sheets, so too little mesh is bought.
- Measuring the slab over the whole floor area although it is confined between tie beams and does not run over them on the drawings.
- Neglecting to saw the joints in time and fill them, then repairing random cracks at the contractor’s cost.
- Pricing a warehouse floor with an ordinary finish although the specification calls for high flatness and a surface hardener.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Normal Concrete
Related calculators and terms
More items in Plain concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل