Raft foundation in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Foundation concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for the raft, 80 cm thick, grade C35 with sulphate-resisting cement, placed by pumps in a continuous pour under an approved pour plan that controls concrete temperature; the rate includes bottom and top reinforcement, chairs for the top mat, starter bars for columns and walls, edge formwork, waterstops at construction joints and curing.
Method of measurement
The raft area is measured to its outer faces and multiplied by its thickness; thickenings under columns and around lift pits and pump rooms are added at their net volumes, and recesses and pits that reduce the thickness are deducted. Small pipe positions and the volume of steel are not deducted. Walls and columns rising from the top of the raft are measured under their own items.
What the unit rate covers
- Concrete and continuous pumping
- Reinforcement, chairs and starter bars
- Edge formwork and stop-ends at construction joints
- Waterstops at joints
- Concrete temperature control and curing
- Finishing the surface to level
Priced separately
- Waterproofing under the raft and its protection layer
- Blinding
- Dewatering during construction
- Piles under the raft, if any
Specification and reference
The raft is designed to the Saudi Building Code SBC 304 and SBC 303, and the code’s hot-weather concreting requirements apply. The project specification sets the mass-concrete controls: concrete temperature at placing and the permitted temperature difference within the mass. Steel complies with ASTM A615 and ready-mix concrete with ASTM C94, and the engineer approves construction joint positions in advance.
What moves the rate
- Raft thickness and volume of each pour
- Steel ratio and weight of chairs
- Temperature control measures required
- Number of construction joints and waterstops
Common pricing mistakes
- Dropping the top-mat chairs from the steel weight; in a thick raft they are heavy, closely spaced bars.
- Forgetting thickenings for lift pits and pump rooms below raft level, which add to concrete, excavation and waterproofing together.
- Pricing the pour at the cost of an ordinary day although a raft is poured at night with several pumps and chilled concrete in summer.
- Ignoring division of the raft into pours and what each joint adds in stop-end formwork, waterstop and surface preparation.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete
Related calculators and terms
More items in Foundation concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.