العربية Try the demo Start now
Home › BOQ items guide › Concrete works › Foundation concrete › Raft foundation

Raft foundation in the bill of quantities

Unitm³
CategoryFoundation concrete
DivisionConcrete works

The item as worded in the bill

Supply and pour reinforced concrete for the raft, 80 cm thick, grade C35 with sulphate-resisting cement, placed by pumps in a continuous pour under an approved pour plan that controls concrete temperature; the rate includes bottom and top reinforcement, chairs for the top mat, starter bars for columns and walls, edge formwork, waterstops at construction joints and curing.

Method of measurement

The raft area is measured to its outer faces and multiplied by its thickness; thickenings under columns and around lift pits and pump rooms are added at their net volumes, and recesses and pits that reduce the thickness are deducted. Small pipe positions and the volume of steel are not deducted. Walls and columns rising from the top of the raft are measured under their own items.

What the unit rate covers

Priced separately

Specification and reference

The raft is designed to the Saudi Building Code SBC 304 and SBC 303, and the code’s hot-weather concreting requirements apply. The project specification sets the mass-concrete controls: concrete temperature at placing and the permitted temperature difference within the mass. Steel complies with ASTM A615 and ready-mix concrete with ASTM C94, and the engineer approves construction joint positions in advance.

What moves the rate

Common pricing mistakes

A published price for its main material

The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete

Related calculators and terms

More items in Foundation concrete