Tie beams (ground beams) in the bill of quantities
| Unit | m³ (or lin. m by section) |
|---|---|
| Category | Foundation concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for ground tie beams linking the column necks, 30×60 cm in section, grade C30 with sulphate-resisting cement, as shown on the tie-beam plan; the rate includes longitudinal steel, stirrups, side formwork, vibration, curing, two coats of bitumen to faces in contact with fill, and leaving sleeves for pipes.
Method of measurement
The volume of a tie beam is its section multiplied by its clear length between the faces of the column necks; length is not measured centre to centre. Where two tie beams cross, one is taken through and the other stops at its face. Tie beams are grouped by their types on the drawing because section and reinforcement differ. Small pipe sleeves are not deducted.
What the unit rate covers
- Ready-mix concrete, placing and vibration
- Longitudinal steel and stirrups
- Side formwork to the beam
- Bitumen paint to faces in contact with fill
- Pipe sleeves
Priced separately
- Blinding under the tie beams
- Excavation and backfilling
- Damp-proof course and masonry above the tie beam
Specification and reference
Tie beams are designed and built to the Saudi Building Code SBC 304, with the foundation requirements of SBC 303 observed. Steel complies with ASTM A615, and the soil report sets the cement type. The drawings show whether the beam is cast on blinding or directly on soil, and whether it carries ground-floor walls or only ties the footings.
What moves the rate
- Beam section and steel ratio
- Different tie-beam levels in the building
- Number of types and total length
- Pouring with the necks or in a separate stage
Common pricing mistakes
- Measuring the tie beam from column centre to centre, so the junction volume is counted twice with the necks.
- Overlooking internal tie beams under partitions and the stair because they appear only on the structural tie-beam plan.
- Pricing soffit formwork for a tie beam cast on blinding, or forgetting the blinding beneath it in the plain concrete item.
- Ignoring dropped tie beams at entrances and the garage, which add to excavation, neck height and the masonry above them.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete
Related calculators and terms
More items in Foundation concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل