Tie beams (ground beams) in the bill of quantities

Unitm³ (or lin. m by section)
CategoryFoundation concrete
DivisionConcrete works

The item as worded in the bill

Supply and pour reinforced concrete for ground tie beams linking the column necks, 30×60 cm in section, grade C30 with sulphate-resisting cement, as shown on the tie-beam plan; the rate includes longitudinal steel, stirrups, side formwork, vibration, curing, two coats of bitumen to faces in contact with fill, and leaving sleeves for pipes.

Method of measurement

The volume of a tie beam is its section multiplied by its clear length between the faces of the column necks; length is not measured centre to centre. Where two tie beams cross, one is taken through and the other stops at its face. Tie beams are grouped by their types on the drawing because section and reinforcement differ. Small pipe sleeves are not deducted.

What the unit rate covers

Priced separately

Specification and reference

Tie beams are designed and built to the Saudi Building Code SBC 304, with the foundation requirements of SBC 303 observed. Steel complies with ASTM A615, and the soil report sets the cement type. The drawings show whether the beam is cast on blinding or directly on soil, and whether it carries ground-floor walls or only ties the footings.

What moves the rate

Common pricing mistakes

A published price for its main material

The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete

Related calculators and terms

More items in Foundation concrete

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل