العربية Try the demo Start now
Home › BOQ items guide › Concrete works › Plain concrete › Blinding concrete

Blinding concrete in the bill of quantities

Unitm² of stated thickness (or m³)
CategoryPlain concrete
DivisionConcrete works

The item as worded in the bill

Supply and pour plain concrete (blinding) under footings, tie beams and raft, 10 cm thick, with a cylinder strength of not less than 20 MPa at 28 days, using sulphate-resisting cement, projecting 10 cm beyond the reinforced concrete on every side and finished level; the rate includes side forms and curing.

Method of measurement

The horizontal area of the blinding is measured as drawn, that is the foundation dimensions plus the specified projection on every side, and multiplied by the theoretical thickness where the item is in cubic metres. Extra thickness caused by over-excavation or an uneven bottom is not paid. Blinding under tie beams is measured over its net length between footings so that no area is counted twice.

What the unit rate covers

Priced separately

Specification and reference

The concrete is subject to the durability and cement-type requirements of the Saudi Building Code SBC 304 according to its sulphate exposure as shown in the soil report. Cement complies with ASTM C150 and ready-mix concrete with ASTM C94. The project specification sets the strength and thickness, and test samples are taken under the approved inspection plan.

What moves the rate

Common pricing mistakes

A published price for its main material

The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 250 K Resistant Concrete

Related calculators and terms

More items in Plain concrete

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل