Blinding concrete in the bill of quantities
| Unit | m² of stated thickness (or m³) |
|---|---|
| Category | Plain concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour plain concrete (blinding) under footings, tie beams and raft, 10 cm thick, with a cylinder strength of not less than 20 MPa at 28 days, using sulphate-resisting cement, projecting 10 cm beyond the reinforced concrete on every side and finished level; the rate includes side forms and curing.
Method of measurement
The horizontal area of the blinding is measured as drawn, that is the foundation dimensions plus the specified projection on every side, and multiplied by the theoretical thickness where the item is in cubic metres. Extra thickness caused by over-excavation or an uneven bottom is not paid. Blinding under tie beams is measured over its net length between footings so that no area is counted twice.
What the unit rate covers
- Ready-mix concrete of the specified strength and cement type
- Placing, spreading and levelling
- Simple side forms
- Water curing
- Pump or other means of handling
Priced separately
- Polyethylene sheet under the blinding
- Waterproofing over the blinding and its protection layer
- Compacting the excavation bottom and treating the soil
Specification and reference
The concrete is subject to the durability and cement-type requirements of the Saudi Building Code SBC 304 according to its sulphate exposure as shown in the soil report. Cement complies with ASTM C150 and ready-mix concrete with ASTM C94. The project specification sets the strength and thickness, and test samples are taken under the approved inspection plan.
What moves the rate
- Thickness and cement type
- Scatter of footings and number of pours
- Evenness of the excavation bottom
- Truck-mixer access or need for a pump
Common pricing mistakes
- Measuring on the footing dimensions themselves without the 10 cm projection on each side, which clearly understates small footings.
- Pricing an item whose unit is the square metre at a cubic-metre rate, or the reverse, through not noticing the unit in the bill.
- Overlooking blinding to tie beams, lift pits and the underground tank and taking only the footings visible on the foundation plan.
- Ordering concrete for exactly the theoretical thickness, although an uneven excavation bottom always consumes more.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 250 K Resistant Concrete
Related calculators and terms
More items in Plain concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل