Isolated footings in the bill of quantities

Unitm³
CategoryFoundation concrete
DivisionConcrete works

The item as worded in the bill

Supply and pour reinforced concrete for isolated and combined footings, grade C30 with sulphate-resisting cement, to the dimensions and reinforcement shown on the foundation plan and footing schedule, with 7.5 cm cover; the rate includes reinforcement, column starter bars, side formwork, vibration, curing and two coats of bitumen to faces touching the soil.

Method of measurement

The net volume is measured from the drawings: footing length by width by thickness, multiplied by the number of footings of each type in the footing schedule. Sloped or stepped footings are taken at their true geometric volumes. The volume of steel is not deducted and nothing is added for concrete poured beyond the forms. Column necks are measured from the top of the footing under their own item.

What the unit rate covers

Priced separately

Specification and reference

Footings are designed and built to the Saudi Building Code SBC 304 for concrete structures and SBC 303 for soils and foundations. The code requires at least 75 mm cover for concrete cast directly against the soil. Reinforcement complies with ASTM A615 and cement with ASTM C150, of the type set by the sulphate exposure in the soil report.

What moves the rate

Common pricing mistakes

A published price for its main material

The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete

Related calculators and terms

More items in Foundation concrete

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل