Column necks in the bill of quantities
| Unit | m³ |
|---|---|
| Category | Foundation concrete |
| Division | Concrete works |
The item as worded in the bill
Supply and pour reinforced concrete for column necks from the top of the footings to the top of the tie beams, to the sections shown in the column schedule, grade C30 with sulphate-resisting cement; the rate includes reinforcement, ties, formwork and its bracing, vibration, curing and two coats of bitumen to buried faces.
Method of measurement
The neck volume is its section multiplied by its height from the top of the footing to the top of the tie beam, the height being taken for each neck from the actual level of its footing, not one value for all. Its junction with the tie beams is included in its volume. Where the neck section differs from the column above, the section shown for the neck is used.
What the unit rate covers
- Ready-mix concrete placed in small pours
- Vertical bars and ties
- Formwork and its bracing
- Vibration and curing
- Bitumen paint to buried faces
Priced separately
- Footings and tie beams
- Columns above tie-beam level
- Backfilling around the necks
Specification and reference
Necks are built to the Saudi Building Code SBC 304 and treated as concrete exposed to soil as regards cover and cement type according to the soil report. Steel complies with ASTM A615, and the drawings show the lap length of the column starter bars above tie-beam level. The project specification sets the type of protection to buried faces.
What moves the rate
- Founding depth and neck height
- Neck section and steel ratio
- Number of necks and small pour volume
- Variation in footing levels
Common pricing mistakes
- Using one height for all necks although footing levels vary on sloping ground or beside the tank.
- Calculating the neck at the section of the column above although the column schedule enlarges it below ground for extra cover.
- Pricing necks at the rate of floor columns although their pours are small and scattered and attract part-load charges and pump hire.
- Forgetting that neck steel projects above tie-beam level by the lap length to splice with the ground-floor column steel.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete
Related calculators and terms
More items in Foundation concrete
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل