Precast hollow-core slabs in the bill of quantities
| Unit | m² |
|---|---|
| Category | Precast concrete and tanks |
| Division | Concrete works |
The item as worded in the bill
Supply and erect precast prestressed hollow-core concrete slabs 20 cm thick and 120 cm wide, designed for the spans and loads shown on the drawings, including transport, lifting by crane, placing on bearing pads and grouting the longitudinal joints with cement grout; the rate includes design calculations, shop drawings and factory-formed openings.
Method of measurement
The horizontal area covered by slabs actually erected is measured, and the contract states whether the bearing length on the beams is counted in the area or the clear area between their faces is taken. Large openings are deducted; small factory-formed openings are not. Slabs cut lengthwise are measured at their actual area. The topping is measured under a separate item.
What the unit rate covers
- Design and shop drawings
- Manufacture and transport to site
- Crane and erection
- Bearing pads
- Grouting longitudinal joints
- Factory-formed openings
Priced separately
- Concrete topping and its mesh
- Supporting beams and walls
- Concreting slab ends and tie steel to beams
- Preparing the crane access and standing
Specification and reference
Precast prestressed elements are designed to the Saudi Building Code SBC 304 for the loads set in SBC 301, and the manufacturer submits calculations and shop drawings for approval before production. The project specification and the manufacturer’s data set the minimum bearing length, the fire resistance required and the permitted camber, and the plant must be approved by the engineer.
What moves the rate
- Slab thickness, span and load
- Distance from the plant to the site
- Crane access and erection height
- Number of cut slabs and openings
Common pricing mistakes
- Comparing the rate per metre of hollow-core with a cast slab without adding the topping, its mesh and the end concreting.
- Assuming all slabs can be erected by one crane from one position, although the crane’s reach does not cover the building.
- Overlooking that slabs cut to make up the width are usually charged by the manufacturer at full slab width.
- Building the supporting beams with level differences beyond tolerance, then correcting them by thickening the topping.
Related calculators and terms
More items in Precast concrete and tanks
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل