Underground concrete water tank in the bill of quantities
| Unit | m³ (or lump sum for a stated capacity) |
|---|---|
| Category | Precast concrete and tanks |
| Division | Concrete works |
The item as worded in the bill
Supply and pour watertight reinforced concrete for the underground tank (base, walls and roof), grade C35 with sulphate-resisting cement and a waterproofing admixture; the rate includes reinforcement, formwork, waterstops at construction joints, pipe sleeves, the access opening with its cover, and a water test before backfilling.
Method of measurement
Concrete to base, walls and roof is measured net from the drawings: the base over its full area by its thickness, the walls over their height from base top to roof soffit, and the roof over its area less the access opening. Haunches where walls meet the base are added. A lump-sum item is not measured; the description and drawings define what the rate covers.
What the unit rate covers
- Concrete with waterproofing admixture
- Reinforcement and inner and outer formwork
- Waterstops at construction joints
- Pipe sleeves and access opening
- Water test and repair of leaks
Priced separately
- Excavation, blinding and backfilling
- Internal lining suitable for drinking water
- External waterproofing to faces touching the soil
- Pumps, float valves and pipework
Specification and reference
The tank is designed to the Saudi Building Code SBC 304 with tighter crack control as a water-retaining structure; a well-known reference for this is ACI 350. The SBC 701 requirements for protecting drinking water from contamination are observed. The project specification sets the duration of the water test and the acceptable drop in water level.
What moves the rate
- Tank capacity and depth
- Wall thickness and steel ratio
- Groundwater level
- Type of internal and external waterproofing required
Common pricing mistakes
- Calculating concrete and excavation from the required water capacity without the wall and base thicknesses and the freeboard above the water surface.
- Pricing tank steel at the ratio for ordinary walls although crack control demands more steel at closer spacing.
- Neglecting the water test, the cost of its water and the wait before backfilling, then finding leaks after the walls are buried.
- Forgetting the waterstop at the construction joint between base and walls, the point of the tank most prone to leaking.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 350 K Resistant Concrete
Related calculators and terms
More items in Precast concrete and tanks
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل