Formwork in the bill of quantities
| Unit | m² of contact area |
|---|---|
| Category | Reinforcement and formwork |
| Division | Concrete works |
The item as worded in the bill
Supply, erect and strike formwork to concrete elements, of water-resistant plywood sheets 18 mm thick on timber battens or of steel panels, with steel props and ties, tight at the joints and resisting the pressure of placing without distortion; the rate includes release agent, chamfer strips, forming openings, cleaning and reuse.
Method of measurement
The actual contact area between form and concrete is measured for each element: sides of footings and tie beams, column perimeters by their height, both faces of walls, slab soffits between beams, and beam sides and soffits. Surfaces cast against soil or blinding and top surfaces are not measured. Small openings defined by the method of measurement are not deducted, and stop-ends at construction joints are not measured.
What the unit rate covers
- Sheets and battens or steel panels
- Props and ties
- Erection, alignment and striking
- Release agent and chamfer strips
- Forming openings and stop-ends
- Cleaning and moving between floors
Priced separately
- Load-bearing scaffolding to high slabs where given its own item
- Special formwork for architectural fair-faced concrete
- Waterstops and embedded items
Specification and reference
The Saudi Building Code SBC 304 sets the requirements for formwork design, striking and re-propping, and a well-known design reference is the ACI 347 guide. The project specification sets the surface finish class, the permitted tolerances in dimension and plumb, and the minimum periods before striking side forms and props; safety requirements apply during erection and striking.
What moves the rate
- Element type and formwork area relative to concrete volume
- Number of reuses of the sheets
- Propping height
- Surface finish required
Common pricing mistakes
- Assuming many reuses of plywood although fair-faced concrete and repeated cutting ruin it quickly.
- Loading formwork onto the concrete rate at one value for all elements, although a wall needs several times more per cubic metre than a raft.
- Pricing slab propping with ordinary props although the storey height exceeds their range and needs scaffold towers.
- Measuring slab soffit formwork over the whole area without deducting the beams whose formwork is measured under their own item.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: Indonesian Ablakash Wood
Related calculators and terms
More items in Reinforcement and formwork
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل