Shoring of excavation sides in the bill of quantities
| Unit | m² of retained face (or lin. m) |
|---|---|
| Category | Shoring and dewatering |
| Division | Site preparation and earthworks |
The item as worded in the bill
Design, supply and install a temporary shoring system to the basement excavation sides, 6 m deep, of contiguous concrete piles 60 cm in diameter with a capping beam and ground anchors, to the soil report and the design approved by the engineer; the rate includes shop drawings, calculations, movement monitoring and de-stressing the anchors when no longer needed.
Method of measurement
The retained face is measured: the length along the shoring line multiplied by the height from the top of the shoring to the final bottom of excavation. The part embedded below the bottom, the anchors and the capping beam are not measured separately unless items are given for them. Where the item is per linear metre, the shored perimeter is measured and the depth stated in the description.
What the unit rate covers
- Design, calculations and shop drawings
- Piles or soldier posts and lagging
- Capping beam and anchors or struts
- Monitoring points and their regular readings
- Condition survey of neighbouring buildings
- Removing temporary elements when no longer needed
Priced separately
- Bulk excavation inside the shoring
- Groundwater dewatering
- Waterproofing of basement walls
- Underpinning foundations of neighbouring buildings
Specification and reference
The shoring system is designed to the Saudi Building Code SBC 303 for soils, foundations and retaining walls, and its concrete elements to SBC 304, based on the soil properties and water level in the soil report. Municipalities require the shoring drawings to be approved by a qualified engineering office before excavating next to adjoining properties and streets.
What moves the rate
- Excavation depth and soil type
- Shoring system chosen and number of anchor rows
- Closeness of neighbouring buildings and their loads
- How long the shoring stays before the basement walls are complete
Common pricing mistakes
- Pricing the square metre on the exposed pile length only and forgetting that the embedment below the bottom is built but not paid.
- Assuming ground anchors may run under the neighbour’s land without consent, then switching to costlier internal struts.
- Overlooking the clash between internal struts and the pouring of walls and slabs, with the staged removal and re-propping that follows.
- Choosing the shoring system before knowing the water level, although contiguous piles do not stop water seeping through their gaps.
Related calculators and terms
More items in Shoring and dewatering
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل