Shoring and dewatering in the bill of quantities
These works are needed when safe sloped sides cannot be cut or the excavation bottom lies below groundwater level. Shoring is built with contiguous or secant piles, steel soldier posts with lagging, steel sheet piles, or shotcrete with soil nails, supported by ground anchors or internal struts as depth increases. Dewatering is done by open sump pumps where the water is only slightly above the bottom, and by wellpoints or deep wells where it is high. A specialist contractor chooses the system from the soil report.
Where it sits in the bill and what comes before it on site
Its items sit within the earthworks or in a separate specialist section. Shoring is installed before bulk excavation, and dewatering starts before the excavation reaches the water level. Both are preceded by approval of the design and a recorded survey of neighbouring buildings.
Items in this category
| Item | Unit |
|---|---|
| Shoring of excavation sides | m² of retained face (or lin. m) |
| Groundwater dewatering | lump sum (or per day or month of operation) |
What is often left out when pricing it
- Design of the shoring system and its approval by a qualified engineering office, which most contracts place on the contractor.
- Monitoring shoring movement and settlement of neighbouring buildings by regular readings throughout the excavation.
- Running the pumps around the clock with a standby generator, standby pumps, fuel and shift attendants.
- The permit to discharge pumped water and the discharge line to the point approved by the competent authority.
Frequently asked questions
How is dewatering priced: as a lump sum or by running time?
Fairest to both parties is a lump-sum item for installing and removing the system and another for running it per day or month. Where the whole item is a lump sum, the contractor estimates the running period from the programme until enough structure is complete to resist uplift, plus a margin for delay.
Is the embedded part of shoring piles below the excavation bottom measured?
Where the item is per square metre of retained face, the part embedded below the bottom is not measured and its cost is carried in the rate for the exposed square metre. Where it is per linear metre of pile, the full designed length is measured. The item description states which method applies.
Who bears damage to neighbouring buildings during deep excavation?
In principle the contractor, as long as shoring design and execution are his responsibility. He therefore records the condition of neighbouring buildings with photographs and signed reports before starting, installs monitoring points read regularly and checks that the insurance covers such damage. These costs belong in the rate even if the item omits them.
Related calculators and terms
Other categories in Site preparation and earthworks
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل