Groundwater dewatering in the bill of quantities
| Unit | lump sum (or per day or month of operation) |
|---|---|
| Category | Shoring and dewatering |
| Division | Site preparation and earthworks |
The item as worded in the bill
Supply, install, operate and maintain a groundwater dewatering system of wellpoints or deep wells to lower the water level to not less than 50 cm below the bottom of excavation, with duty and standby pumps, generator, discharge line and settlement tank, running continuously until the engineer approves stopping, including the discharge permit and removal of the system.
Method of measurement
Installation and removal of the system are paid as one lump sum, and operation is paid by time from the recorded start of pumping to the date the engineer approves stopping, where the bill separates the two. The number of wells or pumps and the volume of water pumped are not measured. Periods when the system is down through breakdown or lack of fuel are not paid.
What the unit rate covers
- Wells, pipework and pumps
- Standby pumps and generator
- Discharge line and settlement tank
- Fuel, operation and round-the-clock attendance
- Discharge permit
- Removing the system and filling the wells
Priced separately
- Shoring of the excavation sides
- Waterproofing of the raft and basement walls
- Treating the pumped water if the competent authority requires it
Specification and reference
The dewatering design rests on the groundwater level and soil permeability in the investigation report prepared under the Saudi Building Code SBC 303, and on the project specification. A permit from the municipality or the drainage network owner is required before discharging into it. Dewatering is not stopped until the structural engineer confirms that the structure’s weight resists uplift.
What moves the rate
- Height of water above the bottom and soil permeability
- Running period until stopping
- Distance to the approved discharge point
- Area and perimeter of the excavation
Common pricing mistakes
- Pricing operation only until the raft is poured, although stopping is not allowed before enough weight of structure is in place.
- Relying on a water-level reading from a borehole taken in summer although the level rises after rainy seasons.
- Leaving out the standby generator and pumps, although a few hours without pumping floods the excavation and ruins the waterproofing.
- Forgetting the effect of drawdown on settlement of neighbouring buildings and the monitoring or recharge wells that follow.
Related calculators and terms