Groundwater dewatering in the bill of quantities

Unitlump sum (or per day or month of operation)
CategoryShoring and dewatering
DivisionSite preparation and earthworks

The item as worded in the bill

Supply, install, operate and maintain a groundwater dewatering system of wellpoints or deep wells to lower the water level to not less than 50 cm below the bottom of excavation, with duty and standby pumps, generator, discharge line and settlement tank, running continuously until the engineer approves stopping, including the discharge permit and removal of the system.

Method of measurement

Installation and removal of the system are paid as one lump sum, and operation is paid by time from the recorded start of pumping to the date the engineer approves stopping, where the bill separates the two. The number of wells or pumps and the volume of water pumped are not measured. Periods when the system is down through breakdown or lack of fuel are not paid.

What the unit rate covers

Priced separately

Specification and reference

The dewatering design rests on the groundwater level and soil permeability in the investigation report prepared under the Saudi Building Code SBC 303, and on the project specification. A permit from the municipality or the drainage network owner is required before discharging into it. Dewatering is not stopped until the structural engineer confirms that the structure’s weight resists uplift.

What moves the rate

Common pricing mistakes

Related calculators and terms

More items in Shoring and dewatering

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.

Start nowجرّب بلا تسجيل