Earthing and low-current systems in the bill of quantities
This category gathers the safety and communications systems. Earthing discharges fault current to ground and bonds metal parts equipotentially; lightning protection intercepts the strike and conducts it to earth by a safe path. Low-current systems comprise the fire alarm, which is subject to Civil Defense approval, surveillance cameras and the data and telephone network; public address, access control and television may be added. These systems are usually supplied and programmed by a specialist subcontractor, while the main contractor remains responsible for conduits and coordination.
Where it sits in the bill and what comes before it on site
Listed at the end of the electrical bill, each system in its own section. Earthing is executed with the foundations and excavation, low-current conduits are laid with power conduits on separate routes, and devices are installed and programmed after finishes, once permanent power is available.
Items in this category
| Item | Unit |
|---|---|
| Earthing system | lump sum (or No. for pits and lin. m for conductors) |
| Lightning protection | lump sum (or lin. m for conductors and No. for terminals) |
| Fire alarm system | No. for devices and lin. m for cables (or lump sum) |
| CCTV system | No. for cameras and equipment (or lump sum) |
| Data and telephone network | point (or lin. m for cables and No. for outlets) |
What is often left out when pricing it
- Programming, commissioning and training the owner’s operators, with operation and maintenance documents and as-built drawings for every system.
- The accredited engineering office’s fees for preparing the fire drawings and getting them approved by Civil Defense.
- Standby batteries and uninterruptible power units for alarm panels, recorders and network switches.
- Racks, brackets, patch panels and patch cords inside the communications rooms.
Frequently asked questions
Do I price low-current systems per point or as a lump sum?
Both occur. The more accurate bill lists devices, panels and racks by number and cables by the metre, then an item for programming and commissioning. For a lump sum, ask the specialist supplier for a quotation based on the drawings and specification, and check it covers cables, conduits, licences, programming and warranty, not just devices.
What earth resistance must I achieve, and what if it is not reached?
The specification and electricity company requirements set the maximum acceptable value, measured after installation in the engineer’s presence. In rocky or dry sandy soil the rods shown on the drawings may not suffice, and extra or deeper rods or soil-enhancing material are needed. Read the soil report, and ask before tendering who bears the increase.
Where does the main contractor’s work end and the subcontractor’s begin in these systems?
Normally the main contractor lays conduits, boxes and containment within the electrical works, and the specialist supplies cables, devices and panels and programs and commissions. Contracts vary, though, and cables may fall to either party. Write the scope boundary into the subcontract item by item, above all power supplies, openings and fire-stopping of penetrations.
Related calculators and terms
Other categories in Electrical works
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل