Data and telephone network in the bill of quantities
| Unit | point (or lin. m for cables and No. for outlets) |
|---|---|
| Category | Earthing and low-current systems |
| Division | Electrical works |
The item as worded in the bill
Supply and install a Category 6 (Cat6) data point of a four-pair unshielded twisted-pair copper cable from the communications cabinet to the outlet, not exceeding 90 m, a wall outlet with RJ45 jack and faceplate, and termination on the patch panel in the cabinet; the rate includes labelling at both ends, certification testing of every point and its reports.
Method of measurement
Measured per point for each outlet; a twin outlet is two points because every jack has its own cable back to the cabinet. Where the bill separates them, cables are measured in linear metres on the actual route in the containment with rises and drops, outlets, patch panels and cabinets by number, backbone optical fibre cables between cabinets in linear metres stating the core count, and fibre terminations by number.
What the unit rate covers
- Twisted-pair cable from cabinet to outlet
- Jack, faceplate and box
- Termination on the patch panel
- Labelling at both ends
- Certification test and its report
Priced separately
- Switches, routers and active network equipment
- Cabinets, patch panels and patch cords
- Backbone optical fibre and the service provider’s line
Specification and reference
Executed to ISO/IEC 11801 for structured cabling, which limits the horizontal permanent link to ninety metres, and to SBC 401 for earthing and separation from power. Components are of one category from a source granting a system warranty, every point is tested with a calibrated certifier, and the service provider’s requirements for the entrance room and incoming fibre are observed.
What moves the rate
- Cable category: 6 or 6A, shielded or unshielded
- Average point length and number of cabinets
- Standard or low-smoke halogen-free sheath
- Requirement for a manufacturer’s system warranty
Common pricing mistakes
- Counting a twin outlet as one point when each of its jacks has a full cable, termination and separate test.
- Ignoring the ninety-metre limit, so remote points fail the test and an additional communications cabinet is needed on the floor.
- Forgetting points for wireless access points, cameras, access readers and display screens, located in the ceiling, not on the wall outlet layout.
- Pricing the test as a simple continuity check when the specification requires certification with a calibrated tester and a report for every point.
Related calculators and terms
More items in Earthing and low-current systems
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل