Fire alarm system in the bill of quantities
| Unit | No. for devices and lin. m for cables (or lump sum) |
|---|---|
| Category | Earthing and low-current systems |
| Division | Electrical works |
The item as worded in the bill
Supply, install, program and commission an addressable fire alarm system comprising a two-loop main control panel with standby batteries, addressable smoke and heat detectors, manual call points, sounders with strobes, and interface modules to the air-conditioning, lift and fire pump systems; the rate includes fire-resistant cables, testing and Civil Defense approval.
Method of measurement
Devices are measured by number for each type: smoke detector, heat detector, duct detector, call point, sounder, strobe, interface module; the control panel and repeater panels by number. Cables are measured in linear metres along the loop route out and back to the panel, or carried in the rate per point. Programming, commissioning and Civil Defense approval form a lump sum item or are spread over the devices.
What the unit rate covers
- Control panel, batteries and charger
- Detectors with bases and call points
- Sounders, strobes and interface modules
- Fire-resistant cables and their metal fixings
- Programming and testing of every device
- Approval drawings and Civil Defense certificate
Priced separately
- Conduits and boxes where part of the conduit works
- Fire suppression and sprinkler systems
- Connection to a remote monitoring centre and its subscription
Specification and reference
The system is governed by the fire code SBC 801, which sets when an alarm is required by occupancy classification, and by NFPA 72 for design, detector spacing and testing. The General Directorate of Civil Defense requires approval of the drawings, devices listed by a recognised testing body, installation by a licensed contractor, and standby battery supply.
What moves the rate
- Addressable or conventional, and number of loops
- Number of devices and interface modules
- Cable type and fire-resistance rating
- Voice evacuation or a link to the building management system
Common pricing mistakes
- Counting only detectors visible below the false ceiling and omitting those above ceilings, under raised floors and in air ducts.
- Forgetting interface modules for shutting down air handling units, recalling lifts, releasing secured doors and monitoring sprinkler valves.
- Pricing ordinary cable instead of fire-resistant cable, or measuring the loop one way although it returns to the panel.
- Leaving out the accredited engineering office’s cost, Civil Defense inspection visits and retesting where remarks are raised.
Related calculators and terms