Lightning protection in the bill of quantities
| Unit | lump sum (or lin. m for conductors and No. for terminals) |
|---|---|
| Category | Earthing and low-current systems |
| Division | Electrical works |
The item as worded in the bill
Supply and install a conventional lightning protection system of copper air terminals at the highest roof points, a mesh of 25×3 mm copper tape on the parapet and roof, down conductors on the facades each with a test joint, and dedicated earth electrodes bonded to the building earthing; the rate includes fixings, bonding of metal roof equipment and testing.
Method of measurement
Measured as a lump sum for the complete system to the drawings, or in detail: air terminals by number, roof and down conductors in linear metres on their actual route following the parapet and bends, test joints by number, and earth electrodes by number with their pits. A down conductor runs from roof level to the earth electrode. An early streamer emission head is counted by number with its mast.
What the unit rate covers
- Air terminals and their bases
- Roof and down conductors with their fixings
- Test joints and their boxes
- Earth electrodes and their inspection pits
- Bonding of metal equipment and structures on the roof
- Earth resistance measurement and test certificate
Priced separately
- Surge protective devices inside the boards
- The main building earthing system
- Making good roof waterproofing at fixings unless stated
Specification and reference
The system is designed to IEC 62305 after a risk assessment that sets the protection level, mesh size and down conductor spacing, with earthing and bonding to SBC 401. Materials are copper or aluminium of the standard’s minimum sections, sharp bends are not allowed, the system is bonded to the building earthing, with surge protection at the main board.
What moves the rate
- Protection level and mesh size
- Roof perimeter and building height
- Copper or aluminium, tape or round conductor
- Conventional system or early streamer emission head
Common pricing mistakes
- Measuring roof conductors by the building perimeter alone, omitting the mesh cross lines and the bonding of stair rooms, lift rooms and equipment.
- Assuming only two down conductors when the protection level imposes one at a set spacing round the perimeter, greatly increasing their number.
- Fixing conductors by piercing the roof waterproofing without adhesive or concrete bases, causing leaks for which the contractor is liable.
- Overlooking surge protective devices in the boards, which complete the system and are specified under an item that may not appear here.
Related calculators and terms
More items in Earthing and low-current systems
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل