Earthing system in the bill of quantities
| Unit | lump sum (or No. for pits and lin. m for conductors) |
|---|---|
| Category | Earthing and low-current systems |
| Division | Electrical works |
The item as worded in the bill
Supply and install a complete building earthing system of copper-bonded steel earth rods, 16 mm diameter and 3 m long, in concrete inspection pits with covers, a 70 mm² bare copper conductor linking them around the building, the main earth bar in the electrical room and exothermic welded joints; the rate includes excavation, backfilling, resistance measurement and the test report.
Method of measurement
Measured as a lump sum for the complete system where so billed, or in detail: earth pits by number including rod, pit and cover, bare or insulated copper conductor in linear metres per size, main earth bars by number, and exothermic joints by number or carried in the conductor. The buried conductor is measured on its actual route around the building with the rise to the main bar.
What the unit rate covers
- Earth rods with couplers and driving heads
- Inspection pits and covers
- Copper conductor, clamps and exothermic welds
- Main earth bar and test link
- Trenching and backfilling for the conductor route
- Resistance measurement and test report
Priced separately
- Protective conductors run with cables and circuits
- The lightning protection system
- Soil-enhancing material and extra rods unless stated
Specification and reference
Executed to SBC 401 and the Saudi Electricity Company requirements for the earthing arrangement at the supply point. The specification sets the maximum earth resistance and its method of measurement; equipotential bonding of metal water and gas pipes, structural steel and containment is required, buried joints are exothermically welded, and each pit keeps a disconnecting point for periodic testing.
What moves the rate
- Soil resistivity and number of rods required
- Copper conductor size and route length
- Rock excavation or the need for deep-driven electrodes
- Number of equipotential bonding points
Common pricing mistakes
- Pricing the rod count on the drawing without reading the soil report; dry or rocky soil multiplies the number needed to reach the required resistance.
- Forgetting equipotential bonding of metal pipes, containment and metal door frames in electrical rooms and bathrooms.
- Laying the buried conductor after backfilling and floor casting instead of with the foundations, so excavation is repeated at the contractor’s expense.
- Costing exothermic welds as ordinary clamps, when each joint needs a mould and powder matched to the conductor size and joint shape.
Related calculators and terms
More items in Earthing and low-current systems
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل