Asphalt and roads in the bill of quantities

Asphalt and roads covers the layers of flexible pavement from the bottom up: the aggregate base course compacted over the prepared subgrade, then the asphalt binder and wearing courses with tack coats between them, then the line marking. Layer thicknesses follow traffic and subgrade strength: a single wearing course is enough for light car parks, while streets need a thicker base and two or more asphalt courses. Thermoplastic marking is used on roads, and cold paint in car parks and internal yards.

Where it sits in the bill and what comes before it on site

Items follow the order of work: subgrade preparation, aggregate base, prime coat, asphalt, then marking. Before asphalt, the base compaction and levels must be approved, and kerbstones and service crossings under the road must be complete.

Items in this category

ItemUnit
Aggregate base coursem³ (or m² at a stated thickness)
Asphalt paving coursesm² (or tonne)
Road markinglin. m (lines) and m² (arrows and symbols)

What is often left out when pricing it

Frequently asked questions

Is asphalt measured in square metres or by the tonne?

Most building and municipal bills measure it in square metres per course at a stated compacted thickness; some large road projects measure in cubic metres or tonnes. When measured by area, the contractor bears any excess thickness, so the base level must be set accurately before laying.

What happens if core samples show the asphalt is too thin?

The specification sets a permitted tolerance; a shortfall beyond it is dealt with by a deduction from payment, a compensating layer or removal and relaying, depending on the shortfall and the engineer’s decision. Price the full thickness with a small levelling margin, not the minimum acceptable.

Is base course under kerbstones and shoulders included in the measurement?

Base course is measured to the width shown on the approved cross-section. If it extends under the kerbstones or the shoulder, that extension enters the quantity; if the section does not show it, it is treated as incidental and is not paid. Checking the section before pricing settles the matter.

Related calculators and terms

Other categories in External works and roads

Price your whole bill of quantities

Upload the bill of quantities and its items are priced from published references, each with its price source.