Paving in the bill of quantities
Paving covers the surfacing of paths, yards, car parks and building entrances and their surrounds. Interlocking concrete block is the most widely used because it can be lifted and relaid over buried service lines, and its thickness is chosen by load: pedestrians, cars or lorries. Kerbstones bound the pavement, restrain the edges of the paving and direct rainwater. Stamped concrete is a decorative cast-in-place alternative that suits courtyards and pool surrounds where a continuous surface with few joints is wanted.
Where it sits in the bill and what comes before it on site
Paving items appear in the external works section after site grading and base courses. Before starting, buried service lines must be complete and tested, the base compacted and its levels approved, and kerbstones laid before the interlock is placed.
Items in this category
| Item | Unit |
|---|---|
| Interlocking concrete paving | m² |
| Kerbstones | lin. m |
| Stamped concrete | m² |
What is often left out when pricing it
- Cutting blocks at edges and around manhole covers and columns, with the waste and labour it causes.
- Concrete under and behind kerbstones, which shows neither in the surface area nor on plan.
- Adjusting existing manhole and gully covers to match the finished paving level.
- Bedding sand and joint-filling sand, and plate compaction after the blocks are laid.
Frequently asked questions
Does the rate per square metre of interlock include the base course beneath?
It depends on the item wording. Some bills combine excavation, base course, sand and blocks in one rate; most carry the base course as a separate item in cubic or square metres. Read the description and the paving section on the drawings together before analysing the rate.
How are kerbstones measured on curves?
They are measured in linear metres along the exposed face, curves and corners included. Some bills carry small-radius curves as a separate item because they need short or radiused units and more labour. Dropped kerbs at vehicle entrances are taken off separately where their size differs.
When is stamped concrete preferred to interlock?
When the owner wants a continuous decorative surface imitating stone or timber and no later excavation for services beneath is expected, because repairs leave a visible mark. For car parks and paths over service networks, interlock is the better choice since it can be lifted and relaid.
Related calculators and terms
Other categories in External works and roads
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل