Road marking in the bill of quantities
| Unit | lin. m (lines) and m² (arrows and symbols) |
|---|---|
| Category | Asphalt and roads |
| Division | External works and roads |
The item as worded in the bill
Supply and apply reflective thermoplastic longitudinal road lines, white, 15 cm wide, to the thickness given in the specification, with premixed and surface-applied glass beads; the rate includes cleaning the asphalt surface, setting out, primer where required and protecting the lines from traffic until hardened.
Method of measurement
Lines are measured in linear metres of length actually painted, for each width and colour, so gaps in broken lines are not counted. Pedestrian crossings, arrows, lettering and hatching are measured in square metres of painted area, or by number for standard arrows and symbols. Parking bay lines are measured in linear metres or per bay as the item states, and reflective road studs by number.
What the unit rate covers
- Marking material and glass beads
- Cleaning and drying the surface
- Setting out and alignment
- Primer on concrete or old asphalt
- Temporary traffic diversion during the work
Priced separately
- Removal of old markings
- Reflective road studs
- Traffic signs and their posts
- Kerb painting
Specification and reference
Governed by the Saudi Highway Code and the traffic control devices manual adopted by the road owner for colours, widths and patterns. Thermoplastic material complies with AASHTO M249 or as the specification states; thickness, glass bead application rate and required retroreflectivity are specified, and marking is applied on a clean, dry surface after new asphalt has fully cured.
What moves the rate
- Marking type (thermoplastic or cold paint) and thickness
- Line width and proportion of special markings
- Quantity and continuity of work
- Working under traffic or on a closed site
Common pricing mistakes
- Measuring a broken line at the full road length, when only the painted length is payable, without the gaps between dashes.
- Pricing cold paint for an item that specifies thermoplastic with glass beads; the two differ widely in material and plant.
- Leaving out the cost of mobilising the thermoplastic machine for small quantities, where the move is spread over few metres.
- Pricing arrows and lettering at the rate for longitudinal lines, although they are applied by hand with stencils and use more material and labour.
Related calculators and terms
More items in Asphalt and roads
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل