Anti-termite soil treatment in the bill of quantities
| Unit | m² (or lump sum) |
|---|---|
| Category | Under-slab soil treatment |
| Division | Site preparation and earthworks |
The item as worded in the bill
Treat the soil against termites by spraying a liquid termiticide approved by the competent authority, at the concentration and application rate recommended by the manufacturer, to the bottoms and sides of foundation excavations, the backfill around them and the soil under the ground slab, by a licensed pest-control firm, with a warranty certificate for the period stated in the specification.
Method of measurement
The horizontal footprint of the building at ground slab level is measured over the outer faces of the tie beams, once only however many spraying stages there are. Excavation sides, foundation faces and the external treatment strip around the building are not measured separately unless the bill splits the stages into items. Re-spraying caused by a delayed pour is not paid.
What the unit rate covers
- Approved termiticide and the water to dilute it
- Spraying at all required stages
- Spraying equipment and protective gear
- Treating the external perimeter of the building
- Warranty certificate
Priced separately
- Treatment of the timber and doors themselves
- Re-treatment after later excavation not shown on the drawings
- Polyethylene sheet over the treated soil
Specification and reference
The item is governed by the project specification, the termiticide data sheet and the label instructions; the product must be registered with the competent authority in the Kingdom and sprayed by a licensed pest-control firm. Each spraying stage is recorded in a report signed by the engineer showing the area treated and the solution used.
What moves the rate
- Number of spraying stages required
- Type of termiticide and warranty period
- Building footprint and foundation depth
- Number of visits by the applicator
Common pricing mistakes
- Pricing one spray under the slab although the specification also calls for spraying the excavation bottom, its sides and the backfill.
- Working out the termiticide on the paid footprint only, although the area actually sprayed, with excavation sides and footings, is larger.
- Spraying the soil and then leaving it exposed for days before the sheet and the pour, so re-spraying falls on the contractor.
- Overlooking the cost of the spraying crew returning several times because backfill and slab are done in parts.
Related calculators and terms
More items in Under-slab soil treatment
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل