Under-slab soil treatment in the bill of quantities
This category joins two works that precede pouring the ground slab: spraying the soil with termiticide and laying polyethylene sheet. The first forms a chemical barrier that stops subterranean termites reaching timber and finishes, and is applied in stages: on the bottom and sides of excavations, then on the backfill, then under the slab. The second is a barrier that stops moisture rising from the soil and keeps the concrete’s water from draining away during the pour. Both are small in the bill, but neither can be corrected afterwards.
Where it sits in the bill and what comes before it on site
Its items come at the end of the earthworks section or with the waterproofing. They are carried out after backfilling and compaction are complete and tested and under-slab services are laid, and immediately before fixing the ground slab reinforcement to avoid damage.
Items in this category
| Item | Unit |
|---|---|
| Anti-termite soil treatment | m² (or lump sum) |
| Polyethylene sheet under concrete | m² |
What is often left out when pricing it
- The several stages of spraying, on excavation bottoms, on backfill and under the slab, rather than one spray before the pour.
- The warranty certificate from a licensed pest-control firm, one of the handover documents the owner asks for.
- Laps of the polyethylene sheet and its edges turned up against tie beams, material that is bought but not measured.
- Re-spraying or replacing torn sheet if the pour is delayed or workers and steel pass over it.
Frequently asked questions
Is termite spraying measured for each stage or only once?
In most bills it is measured once over the building footprint at ground slab level, and the rate covers every spraying stage the specification requires. The contractor therefore works out the real area sprayed at each stage and the solution it needs, then loads this onto the paid square metre.
Is the polyethylene sheet included in the ground slab rate?
It depends on the bill wording: some give it its own item per square metre, others name it in the ground slab or blinding description so that it is carried in that rate. The two descriptions are compared before pricing so that it is neither priced twice nor dropped from the tender.
What voids the termite treatment warranty?
Usually by disturbing the chemical barrier after spraying: digging new service trenches in treated soil, adding untreated fill on top, or flooding it with water before it is covered. Spraying is therefore timed to be followed at once by sheet laying and the pour, and any part dug after treatment is sprayed again.
Related calculators and terms
Other categories in Site preparation and earthworks
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل