Solid blockwork below ground level in the bill of quantities
| Unit | m² (or m³) |
|---|---|
| Category | Concrete block |
| Division | Masonry works |
The item as worded in the bill
Supply and build walls in solid concrete blocks 20 cm thick made with sulphate-resisting cement, laid in 1:3 sulphate-resisting cement and sand mortar, below ground level between footings and under ground beams, with all joints fully filled and surfaces prepared to receive bituminous coating; the rate includes everything necessary.
Method of measurement
Measured in square metres with the thickness stated, or in cubic metres in some bills. Length is taken net between the faces of column necks or footings, and height from the top of the footing or blinding to the ground beam soffit per the sections; it varies as the founding level changes between footings. Nothing is added for excavation width or working space, and waterproofing and backfilling are not covered.
What the unit rate covers
- Supply of solid blocks made with sulphate-resisting cement
- Sulphate-resisting cement mortar with joints fully filled
- Laying inside the excavation in restricted working space
- Finishing the wall faces to receive waterproofing
- Wetting the wall before backfilling
Priced separately
- Bituminous coating or membrane
- Excavation, backfilling and compaction
- Dewatering of groundwater where present
- Blinding concrete under the wall
Specification and reference
The item is governed by Saudi Building Code SBC 305, with the soil investigation report and the requirements of SBC 303 and 304 consulted to fix the cement type by the sulphate and chloride content of the soil and groundwater, which is high in sabkha and coastal areas. The project technical specification sets the block strength and the mortar mix.
What moves the rate
- Cement type required in the block and mortar
- Founding depth and restricted working space in the excavation
- Presence of groundwater during laying
- Wall thickness and its varying height
Common pricing mistakes
- Pricing solid block at the hollow block rate although it is heavier, richer in cement and slower to lay.
- Taking a single height for all walls although footing levels differ, so the height changes from one grid line to another.
- Missing the sulphate-resisting cement requirement in the soil report and pricing block and mortar with ordinary cement.
- Forgetting inspection chamber walls and similar small below-ground structures built in the same solid block.
Related calculators and terms