Roof parapet in the bill of quantities
| Unit | lin. m (or m²) |
|---|---|
| Category | Parapets and boundary walls |
| Division | Masonry works |
The item as worded in the bill
Supply and build the roof parapet in hollow concrete blocks 20 cm thick, 1.20 m high above the roof slab level, with concrete stiffener columns tied to dowels from the slab and a reinforced concrete top beam of the wall width; the rate includes mortar, steel, formwork, external scaffolding and openings left for rainwater spouts per the drawings.
Method of measurement
Measured by the linear metre on the parapet centre line, stating the height, where the item is composite, or by the square metre for the blockwork alone with columns and top beam in their own items. Height is taken from the concrete roof slab surface, not finished level. Length covers the perimeters of the main roof, stair room roof and light wells. Small rainwater spout openings are not deducted.
What the unit rate covers
- Blocks and mortar
- Concrete stiffener columns tied to the slab dowels
- Concrete top beam or coping
- Formwork, steel, placing and curing
- External scaffolding and edge protection at the roof perimeter
- Leaving rainwater spout openings
Priced separately
- Plaster and paint to both faces of the parapet
- Waterproofing upstand on the parapet and its termination
- Marble or stone coping where specified
- Expansion joints and their sealant
Specification and reference
Parapet construction is governed by Saudi Building Code SBC 305; its minimum height is set by the guard requirements of SBC 201 and the municipality’s requirements on neighbours’ privacy. Its columns and their fixing to the slab are designed for the wind loads of SBC 301, as it is a wall free at the top. Concrete follows SBC 304.
What moves the rate
- Parapet height and thickness
- Number of storeys below the roof and the external scaffolding and edge protection needed
- Spacing of stiffener columns and section of the top beam
- Dowels present in the slab or needing to be drilled in
Common pricing mistakes
- Taking the parapet length from the ground floor perimeter although the roof outline differs because of setbacks and projections.
- Forgetting the parapet to the stair room and lift room roof, a second roof with its own perimeter.
- Pricing it as ordinary blockwork without the stiffener columns and top beam, which form a large part of the cost.
- Reading parapet height from finished level, so the thickness of the waterproofing, screed and tile layers is lost from it.
A published price for its main material
The monthly Kingdom-wide average as published by the General Authority for Statistics, with its monthly series: 20cm black Block
Related calculators and terms
More items in Parapets and boundary walls
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل