Concrete lintels over openings in the bill of quantities
| Unit | lin. m (or m³) |
|---|---|
| Category | Lintels and wall stiffeners |
| Division | Masonry works |
The item as worded in the bill
Supply and cast reinforced concrete lintels grade C25 over door and window openings in block walls, of the wall width and 20 cm deep, with a bearing of not less than 20 cm at each end, reinforced as shown on the typical detail in the drawings; the rate includes timber formwork, steel reinforcement, placing, curing and striking of formwork.
Method of measurement
Measured by the linear metre per cross-section, or by the cubic metre, lintel length being the structural opening width plus the bearing at both ends. A lintel continuous over adjacent openings is measured as one length. None is measured for an opening directly under a concrete beam. Reinforcement and formwork are not measured separately where the item includes them; otherwise steel goes by weight and formwork by square metre.
What the unit rate covers
- Concrete of the specified grade
- Longitudinal bars and stirrups
- Soffit and side formwork with its propping
- Hand placing, compaction and curing
- Striking formwork after the prescribed period
Priced separately
- Blockwork above and below the lintel
- Plaster
- Steel lintels for wide openings
Specification and reference
Lintels are governed by Saudi Building Code SBC 304 as reinforced concrete members and by SBC 305 as regards their bearing on the wall. Reinforcing steel conforms to ASTM A615, and the typical detail in the structural drawings is followed; it sets the cross-section and reinforcement according to the opening width, and the minimum bearing length.
What moves the rate
- Opening widths and the resulting lintel depth and reinforcement
- Cast in place or precast
- Repetition of sizes and reuse of formwork
- Storey height and scattered pour locations
Common pricing mistakes
- Taking the lintel length as the opening width only, without the bearing at both ends, so the quantity falls short at every opening.
- Counting lintels from the door and window schedule alone and forgetting openings for ducts, electrical panels and fire hose cabinets.
- Allowing lintels for openings that sit directly under downstand beams and need no lintel at all.
- Pricing the cubic metre at the slab concrete rate although placing is by hand in scattered spots and formwork is large for the volume.
Related calculators and terms
More items in Lintels and wall stiffeners
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.