Red clay brickwork in the bill of quantities
| Unit | m² |
|---|---|
| Category | Clay brick |
| Division | Masonry works |
The item as worded in the bill
Supply and build walls in hollow red clay bricks 40×20×20 cm from an approved factory, laid in 1:3 cement–sand mortar, with the bricks wetted before laying and the walls tied to the concrete columns; the rate includes bed-joint reinforcement, cutting, scaffolding, removal of broken bricks off site and everything necessary.
Method of measurement
Measured in square metres of the net wall area after deducting openings, with the thickness stated. Length is taken between column faces and height from the slab to the beam soffit. Nothing is added for transport breakage or cutting, however large; wastage is carried in the unit rate. Exposed facing brick, if any, is measured in a separate item, with its reveals and sills by the linear metre.
What the unit rate covers
- Supply, unloading and storage of bricks on level ground
- Wetting the bricks before laying
- Mortar and laying to line and level
- Column ties and horizontal joint reinforcement
- Scaffolding and hoisting to the floors
- Removal of broken bricks and debris
Priced separately
- Lintels and concrete stiffener columns
- Plaster and paint
- Exposed facing brick and pointing
Specification and reference
The item is governed by Saudi Building Code SBC 305 and the project technical specification, which sets the brick’s compressive strength, water absorption and dimensional tolerances. Mortar conforms to ASTM C270. A factory sample and its test certificate must be approved, and the requirements of SBC 601 or 602 are checked where the brick is used in external walls.
What moves the rate
- Distance of the brick factory from the site and haulage cost
- Brick thickness and strength
- Expected breakage in handling
- Number of openings and amount of cutting
Common pricing mistakes
- Applying the concrete block wastage allowance to clay brick although its breakage in transport and cutting is clearly higher.
- Ignoring haulage from a distant factory when clay brick is not available near the project’s city.
- Confusing hollow clay walling brick with clay hordi blocks made for slabs; they are two different products.
- Pricing the laying without wetting the bricks, so they absorb the mortar water, joints weaken and the work is rejected.
Related calculators and terms
More items in Clay brick