Rubber play surfacing in the bill of quantities
| Unit | m² |
|---|---|
| Category | Play and sports surfaces |
| Division | External works and roads |
The item as worded in the bill
Supply and lay poured-in-place rubber safety surfacing for children’s play areas, total thickness 40 mm, comprising a 30 mm impact-absorbing base layer of recycled black rubber granules and a 10 mm coloured EPDM granule wearing layer, both bound with polyurethane binder; the rate includes primer, trowelling and forming the approved colour pattern.
Method of measurement
Measured in square metres of area actually laid, classified by total thickness. Planting beds, islands and uncovered areas are deducted; equipment posts and their small footings are not. Ramps and mounds are measured on their actual surface. Nothing is added for multiple colours or graphic shapes unless the bill gives them an item, and primer and finishing edges are not measured separately.
What the unit rate covers
- Granules for the base layer and the coloured top layer
- Binder and primer on the base
- Mixing, spreading and hand trowelling
- Forming colours and the borders between them
- Chamfered finishing edges at the perimeter
Priced separately
- Concrete, asphalt or compacted aggregate base
- Surrounding kerbs
- Play equipment and its footings
- Storm drainage under the surfacing
Specification and reference
Governed by the project specification and municipality requirements for public playgrounds. Thickness is set to achieve impact attenuation for the critical fall height of each play item under EN 1177 or ASTM F1292, backed by the manufacturer’s test certificate for the same system. The top layer uses through-coloured, UV-resistant granules, and the surfacing is laid on a dry base.
What moves the rate
- Total thickness tied to fall height
- Number of colours and complexity of graphics
- Binder type and its resistance to yellowing
- Area and condition of the base
Common pricing mistakes
- Pricing one thickness for the whole play area, although fall zones around high equipment need a thicker base layer.
- Costing the coloured top-layer granules at the price of black granules; coloured granules cost clearly more and take more binder.
- Ignoring that summer pouring is confined to morning and evening hours, since high heat speeds binder setting and cuts output.
- Assuming a ready, level base, then making up its dips with extra rubber thickness, the most expensive material in the system.
Related calculators and terms
More items in Play and sports surfaces
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل