Interlocking concrete paving in the bill of quantities
| Unit | m² |
|---|---|
| Category | Paving |
| Division | External works and roads |
The item as worded in the bill
Supply and lay interlocking concrete paving blocks 8 cm thick for car parking, compressive strength as specified, in the approved colour and shape, on a screeded bed of clean sand 3 to 5 cm thick over the compacted base course; the rate includes cutting at edges, filling joints with fine sand and compaction with a plate vibrator.
Method of measurement
Measured in square metres of net paved area between the faces of kerbs and edgings. Planting beds, columns and large manhole covers are deducted according to the deduction limit in the preambles; small openings are not. Nothing is added for cutting waste, multiple colours or pattern; sloping areas are measured on their actual surface, and each thickness has its own item.
What the unit rate covers
- Interlock blocks in the approved thickness and colour
- Sand bedding and its screeding
- Saw cutting at edges and covers
- Joint-filling sand and plate compaction
- Cutting and breakage waste
Priced separately
- Excavation, subgrade preparation and base course
- Kerbstones and concrete edge restraints
- Adjusting manhole cover levels
- Geotextile separator where required
Specification and reference
Governed by the project specification and municipality requirements for public pavements. Blocks comply with ASTM C936 or the corresponding Saudi standard for compressive strength, absorption and dimensional tolerance. Thickness is chosen by load: 6 cm for pedestrians, 8 cm for car traffic and more for heavy loads, and the base course beneath is compacted to the specified degree.
What moves the rate
- Thickness and compressive strength
- Colour, shape and number of colours in the pattern
- Proportion of cutting at edges and curves
- Total area and ease of material access
Common pricing mistakes
- Pricing 6 cm blocks for areas that cars enter while the drawings call for 8 cm, a gap that surfaces at sample approval.
- Ignoring cutting waste in narrow paths, on curves and around covers, where it is far higher than in rectangular yards.
- Assuming the base course is included, or excluded, without reading the paving section and the item description together.
- Forgetting the concrete edge restraint where there is no kerb; without it the paving spreads at the edges and is rejected.
Related calculators and terms
More items in Paving
Price your whole bill of quantities
Upload the bill of quantities and its items are priced from published references, each with its price source.
Start nowجرّب بلا تسجيل